ADMINISTRATIVE ORDER III V G
ADMINISTRATIVE ORDER, In the matter of that certain contract formerly known as
Comptroller's Contract L-7519 for the JULIET-FINN STORM SYSTEM, City Project No.
72-S-1313A, Lametti & Sons, Inc. , Contractor, the specified date of completion is
September 1, 1972, and for reasons beyond the Contractor's control he was not able
to complete the contract by said date of completion, it is hereby
ORDERED, That the City of Saint Paul, through its Mayor, extends the time of completion
to October 31, 1972, provided however, that this Order shall have no force or effect
unless the sureties on the Contractor's bond consent thereto and file such consent in
writing with the Head of the Finance Department of the City of Saint Paul; and it is
FURTHER ORDERED, that the City of Saint Paul does not waive claim for liquidated
damages and engineering and inspection costs on this project may be charged to the
Contractor for such extended period.
•