06-832CITY OF ST. PAIIL
FINAL ORDER
��
Green Sheet No. .38.3���(
In the Matter of improving the area known as Wacouta Commons Park by
installing a 3-Globe and 5-Globe style above standard street lighting system
bounded by Wacouta Street, Eighth Street, Ninth Street and Sibley Street.
Also,
Ir1 the Matter of the Operation Costs of the Above Standard Street Lighting
System for 2007 will be assessed with the Lowertown maintenance area.
under Preliminary Order approved
The Council of the City of Saint Paul has conducted a public hearing
upon the above improvement, due notice thereof having been given as
prescribed by the City Charter; and
WHEREAS, The Council has heard a11 persons, objections and
recommendations pertaining to said proposed improvement and has fully
consiclered the same; now, therefore, be it
RESOLVED, That the Council of the City af Saint Paul does hereby order
that the above-described improvement be made, and the proper City officers
are hereby directed and authorized to proceed with the improvement; and be it
FURTHER RESOLVED, That upon the completion of said improvement, the
proper City officers shall calculate all expenses incurred therein and shall
report the same to the City Council in accordance with Chapter 14 of the City
Charter.
Adopted by the Council: Date: C/-OG —f�f�(o
Certified Passed by the Council Secretary
By .�/_i�.��S�Y/
- /v-
Mayor
Votiag Ward 2
� Green Sheet Green Sheet Green Sheet Green Sheet Green Sheet Green Sheet �
t'�9f6 b �(,�_ �- ��
; DepartmenUOffiee/ une0: � Date IniGated:
Pw -�b>>�Wa� ;,�,��.� Green Sheet NO: 3031301
�
' ConfactPerson&Phone: �
�' Brian V'dek �
�� (
Must Be on Council Agenda by (Date): �
i 26.IUL-06 !
�
Assign
Number
For
Routing
Order
ueoarmient sen[ � o rerson mmawate
o r�n�; we� raw sc �;n i
i S��a ' � Ea�oo i
2 'G'itv Cierk ' S6azi Moore
Tofal # of Signalure Pages _(Clip NI Locations for Signature)
Set date of public hearing to approve installation, operarion and maintenance assessmenu for above standard 3-globe and 5-globe
style street lighting system for the new Wacouta Commons Pazk.
File No.19028
uiations: Appro�e (A) or Reject (R):
Planning Commission
CIB Corttmittee
CiNI Senice Commissian
1. Has this personlfirm e�er vmrked under a coMract for this departmeM?
Yes No
2. Has this perswJfirtn e�er been a city employee?
Yes No
3. Does this persoNfirtn possess a skiil not rrortnaily possessed by arry
current city employee?
Yes No
Explain all yes answers on separeM sheet and attach to green sheet
fnftiating Problem, lssues, Opportunity (Who, WhaR 1Nhen, Where, Why):
Capital River Council and Friends of Wacouta Pazk reques[ed completing the lighting portion of the projec[.
Ailvantages NApproved:
Lighting insiallation will proceed.
Disadvanpges IfApproved:
None identified to date.
Disadvanqqes If Not Approved:
The ]ighting project will not proceed
� ocai wmoun� or �r000
T2nsaction:
Fund�nn source: Cl8 & Assessments
Financial Information:
; (Explain)
Activ'�ty Number:
CosNRevenue Budgeted:
July 10, 2006 3:17 PM Page 1
o�-��
SUMMARY OF ENGINEERING RECOMMENDATIONS
WACOUTA COMMONS PARK
Above Standard Street Lighting System Construction
June 29, 2006
Project
Instaflation of 3-Globe and 5-Globe Style Sireet Lighting System on streets abutting the
new Wacouta Commons Park bounded by Wacouta Street, Eighth Street, Ninth Street
and Sibley Street.
Initiating Action
The project was initiated by the Capital River Council and the Friends of Wacouta Park
to complete the lighting portion of the park project.
Proposed Improvements
It is proposed to install 8 three globe and 7 five globe fixtures on the following streets
abutting Wacouta Commons Park:
West side of Wacouta between 8� and 9� Streets;
East side of Sibley beiween 8� and 9� Streets;
North side of 8� Street between Sibley and Wacouta Streets;
South side of 9 Street between Sibley and Wacouta Streets.
The concrete bases and wiring have already been installed as part of another project.
The area wifl be included in the Lowertown Maintenance Area.
Positive Benefits
The new light installation wil{ match the surrounding street light system and complete
the lighting portion of the project.
Adverse Effects
None.
Time Schedule
Work to be completed late summer / fall 2006
Cost Estimate
Labor and materials
Operation & Maintenance
Estimated Financing
CIB City Wide Lighting Fund
Assessments
$45,000
$ 3,900 per year
$20,000
$25,000
d(�-S� a-
Proposed Assessments
Estimated
Above Standard Assessment $29.76 per assessable foot.
Yearly Operation & Maintenance Assessment $2.50 per assessable fioot.
Source of Additional Information
Brian Vitek at 266-6256
Summary and Recommendations
The Department ofi Public Works believes this is a necessary and worthwhile project
and the Engineering Recommendation is for approval of the project.
�
�
�
�
0
�
�
�
�
�
�
�
�
�