D-5639 wh CITY OF SAINT PAUL
Pink ept.
Canar
OFFICE OF THE MAYOR
No:
ADMINISTRATIVE ORDER /l1
Date: �/
ef
•
ADMINISTRATIVE ORDER, In the matter of that certain contract known as Contract No.
L-8459 for Roadway Improvements in ISABEL-BELLOWS-MORTON-PAGE , City Project No.
80-P-0797D, Ashbach Construction Company , Contractor, the specified date of
completion is 60 calendar days (10-13-80) , and the Contractor did not complete the
contract by said date of completion because of unscheduled and delayed installation
of utilities by others, and it is hereby
ORDERED, That the City of Saint Paul, through its Mayor, extends the time of completion
to July 1, 1981 , provided however, that this Order shall have no force or effect un-
less the sureties on the Contractor's bond consent thereto and file such consent in
writing with the Head of the Finance Department of the City of Saint Paul; and it is
FURTHER ORDERED, That the City of Saint Paul hereby waives all claim for liquidated
damages and that no engineering and inspection costs on this project will be charged to
the Contractor for such extended period.
•
APPROVED AS TO PQRM
..�. 4 /I
Assista•' Sty ttgt Department Head .
Date
11P
Administrative Assistant to Mayor
"Pr OM 01 : 12/1975
Rev: 9/8/76
EXPLANATION OF ADM I N I I_RAT I V ORDERS,
RESOLUTIONS, AND ORDINANCES
•
Date: February 3, 1981
TO: MAYOR GEORGE LATIMER
FR: JOSEPH F. KOENIG, P.W. CONSTRUCTION & STREET DESIGN ENGINEER
RE: Administrative Order for Time Extension
Street Improvements in ISABEL-BELLOWS-MORTON-PAGE
City Project No. 80-P-0707D
Contract No. L-8459
Contractor: Ashbach Construction Company
ACTION REQUESTED:
Modify the contract to change the completion date
Original Completion Date - 60 Calendar Days (October 31, 1980)
Revised Completion Date - July 1, 1981
S
PURPOSE AND RATIONALE FOR THIS ACTION:
Provide additional time for the Contractor to complete work because of delays
caused by utility installation by others.
ATTACHMENTS:
• Administrative Order for Time Extension
JFK:mf