CITY OF SAINT PAUL - OFFICE OF THE MAYOR
ADMINISTRATIVE ORDER
for
CONTRACT CHANGE AGREEMENT NO. 7 (CO #86)
ADMINISTRATIVE ORDER, Whereas, additions which proved to be necessary to the Improvement described
as furnish all meterials. equipment and serv-ic'c nerPccary nr inrilihnta1 far the
concrete and masonr , • . . . , 1 . . - -eu- 1 : ' . '-
known as Contract),-8484-1 3 City Project No. 8195 S , PCL CONSTRUCTION. LTD. ,
Contractor, is composed of the following:
86. Cut and patch concrete walls and roof to allow revisions to freight elevator venting.
ORDERED, That the City of Saint Paul, through its Mayor, approves the foregoing additions made in ac-
cordance with the specifications in the sum of $ 25155 ., said amount to be added to the lump sum con-
sideration named in the contract, known as contract) - R4R4-13 , and which amount is to be financed from:
6 6 01`3
PI R Fund .64 6.00 894 000 re -- u%l'.,,,..h- L 71L eta-& /&c,�,td c-c�•-�1
7 O'Z c'D' ct. -i � lea C,l 4 r "tl ao •
SEE ATTACHED COST ALLOCATION AGREEMENTS
City Cost $1 ,078
Oxford Cost $1 ,077
$2,155
AP" ? ED AS TOFe'M
Slif _ffAt lei _r...,. / _ 7 Qec 0-04,57--x.
Assistant Cit Att∎ ney Contract.Al
4- I/ 1 'IA 19�(� By
'f'�3;::. fs1l . , ADMINISTRATOR I
• r , 9...e4.4.------ Z C' 19 iG `,,u_+vim
f Engine=``— Head �i n51;0 ;nce 1J C
-.4r.1e�i �_ "A_,_.� 19 iikkI�� ''�
Dir=i of ` Aimmist,.t' a Assi t to the Mayor
, �� '
OM 01: 12/1975
Rev. : 9/8/76
EXsPLANATION OF ADMINISTRATIVE ORDERS,
RESOLUTIONS, AND ORDINANCES
• Date: January 15, 1981
ALCOVE ! N
TO: MAYOR GEORGE LATIMER JAN 2 61981�� 0�
FR: Al Amiot s« ,. �F'O��cc<' 4k_o
RE: Contract Change Agreements for Town Square Segment B 44/4.1 6,'6, J96
JS'F`/1.FP
cf.
ACTION REQUESTED:
Approval of Contract Change Agreements No. 7 & 8 to PCL Construction Ltd.
•
PURPOSE AND RATIONALE FOR THIS ACTION :
No. 7 (CO. 86) was a code requirement which was not a part of the original documents.
No. 8 (C0.97) This change was required to add additional landscaping above the
existing stairwells in the loft space. Also included was the
concrete base for the sculpture which was donated. This change
also provided curbs at the base of the round ducts in the loft.
This was necessary to seal the slab.
<,TTACHMENTS:
• Contract Change Agreements No. 7 & 8
Cost Allocation Agreement for No. 7