D-5612 White — City Clerk CITY OF SAINT PAUL
Pink — ce Dept.
Canary— t.
OFFICE OF THE MAYOR
■
No: J ...) 42
ADMINISTRATIVE ORDER
Date: 71/"//4-.8.1
•
ADMINISTRATIVE ORDER, In the matter of that certain contract known as Contract No.
L- 8377 for ST. ANTHONY HILL SEWER REHABILITATION (St. Albans Tunnel) ,
City Project No. 79-S-0971A2 , Lametti & Sons, Inc. , Contractor,
the specified date of completion is January 1, 1981 , and the Contractor did not
complete the contract by said date of completion because of difficulty in scheduling
sub-contractors and because the nature of the project provides only one location of
access for tunnel mining and pouring operations and that made it extremely difficult to
accelerate construction, and it is hereby
ORDERED, that the City of Saint Paul, through its Mayor, extends the time of completion
to April 1, 1981 for all Tunnel Construction Phases and to June 1, 1981 for all Above
Ground Restoration, provided however, that this Order shall have no force or effect un-
less the sureties on the Contractor's bond consent thereto and file such consent in
writing with the Head of the Finance Department of the City of Saint Paul; and it is
FURTHER ORDERED, That the City of Saint Paul does not waive all claim for liquidated
damages and that engineering and inspection costs on this project may be charged to the
Contractor for such extended period.
III
APPROVED AS '• F■ •M
.1.47 _hs/41i i ' ,,,a 2. ,‘ .
, f , 0
f,,,,,.
A• • a t ity A d rn•y Department:He;d
•
c/
/
Date _ ff
A.mini trative Assistant to Mayor
OM 01 : 12/1975
Rev: 9/8/76
EXPLANATION OF ADMINISTRATIVE ORDERS,
TTSOLUTIONS, Fib ORDIN TICES
•
Date: January 7, 1981
TO: MAYOR GEORGE LATIMER JAN 1 31981
FR: JOSEPH F. KOENIG, P.W. CONSTRUCTION & STREET DESIGN ENGINEER
RE: Administrative Order for Time Extension
ST. ANTHONY HILL SEWER REfABILITATION (St. Albans Tunnel)
City Project No. 79-S-0971A2 -
Contract No. L-8377
Contractor: Lametti E Sons, Inc.
ACTION REQUESTED:
Modify the contract to extend the time of completion.
Original Completion Date - January 1, 1981
Revised Completion Date - Tunnel Construction - April 1, 1981
• Above Ground Restoration - June 1, 1981
PURPOSE AND RATIONALE FOR THIS ACTION:
The Contractor did not complete the project by the specified date of completion
because of difficulty in scheduling sub-contractors and because the nature of
the project provides only one location of access for tunnel mining and pouring
operations.
ATTACHMENTS:
Administrative Order for Time Extension
•FK:LHL:mf