D-5604 White - City Clerk No. D .56--;di Pink - Finance Dept. Canary— Dept. Accounting Date /-....---1/ Blue - Engineer Green - Contractor • CITY OF SAINT PAUL - OFFICE OF THE MAYOR ADMINISTRATIVE ORDER for CONTRACT CHANGE AGREEMENT NO. 1 ADMINISTRATIVE ORDER, Whereas, additions which proved to be necessary to the Improvement described as Regrading and Paving of HUMBOLDT-KING DISTRICT 3 CD YEAR 5 known as Contract L- 8330 , City Project No. 79-P-0779A Shafer Contracting Company, Inc. , Contractor, is composed of the following: Item No. 1 thru No. 5 (See Attachment) (Extras not included in original contract) $ 3,316.52 Item No. 6 (See Attachment) $-2,792.50 (Credit Due City) TOTAL ADDITIONS $ 524.02 II ORDERED, That the City of Saint Paul, through its Mayor, approves the foregoing additions made in ac- cordance with the specifications in the sum of $ 524.02 , said amount to be added to the lump sum con- sideration named in the contract, known as contract L- 8330 _, and which amount is to be financed from: No extra funding required due to a reduction in contract quantities. 3ti -03- 177 -i_c_nc______-- APPROVED AS TO F.RM / At Aw'. 19 . .- C,..er-fr C;i7re( C . sista A torney Contr.ctor of /I�///'i p I i/7 19 By _ --..........1 ..'J• Ir`Y"1 -� 5 -, alit lif , impirlirdk • Chief ngineer` H!•.■ • D 747/•.t of ;/ ance 19 _ ''0 -�-C_.— Director of Administrative Assistant to the Mayor _,.Cj OM 01 : 12/1975 Rev: 9/8/76 • EXPLANATION OF AD I N I STRAT I E ORDERS, _...-._ RESOLLiTIDNS, AND ORDINANCES • e41V ° �0 Date: December 12, 1980 OF,j °2 --• oF,0 cE Op 1 L 4,IN FN N2,�F®� \yT T0: MAYOR GEORGE LATIMLR EjyTS R��CE FR: JOSEPH F. KOENIG, P.W. CONSTRUCTION $ STREET DESIGN ENGINEER £S RE: Administrative Order for Contract Change Agreement No. 1 • r.-?4 r- Regrading and Paving of HUMBOLDT-KING DISTRICT 3 CD YEAR 5 City Project No. 79-P-0779A Contract No. L-8330 S Contractor: Shafer Contracting Company, Inc. ACTION REQUESTED: Modify the contract to deduct credit due the City and make payment for extra work to the Contractor. Original Contract Amount $322,432.00 - Extras Per Contract Change Agreement No. 1 524.02 • PURPOSE AND RATIONALE FOR THIS ACTION: The additional work is required to complete the project in a satisfactory manner. This extra work was not anticipated in the original contract. ATTACHMENTS: Change Agreement No. 1 E Attachments Thereto •FK:mf