CONTRACT CHANGE AGREEMENT NO. G-1
ADMINISTRATIVE ORDER, Whereas, additions which proved to be necessary to the Improvement described
as General Construction of the Seal Island Display at Como Zoo
known as Contract L-8103-14-City Project No. 78-58C, James Steele Construction Co. ,
Contractor, is composed of the following:
To place a 4" topping on the surface of the existing slab.
Materials and Labor 5,145.00
Sales Tax 116.00
Insurance 557.00
15% overhead & profit 782.00
Total $6,600.00
•
ORDERED, That the City of Saint Paul, through its Mayor, approves the foregoing additions made in ac-
cordance with the specifications in the sum of $ 6,600.00 _, said amount to be added to the lump sum con-
sideration named in the contract, known as contract L 8103-14 _, and which amount is to be financed from:
SUMMARY
Original Contract Sum $ 221 ,900.00 60300
Change Orders to Date $ 0 (L-8103-1 )
Amount this Change Order---+ $ 6,600.00
New Contract Sum $ 228,500.00
.. . . 5 ✓ , I
O
�0 , /2 - 10 James Steele Construction Co.
..� , � � 1719
•#1! ant Cit •�•rney Contractor
1/ „ ` %_ 19 By 4 ter da,mg210-31-80 (Attached)
Fogtam City Architect Pr lir
_ 19 Air 7Z c /, „._,.-';
• Chief E gine / ea. • Deparlit of F.i :nce
I irector of C munity Ser./ ces Administrative Assistant to the Mayor
�� O
"� ► '� i OM O1: 12/1975
Rev. : 9/8/76
EXPLANATION OF ADMINISTRATIVE ORDERS,
RESOLUTIONS, AND ORDINANCES
10 !%rep
DEC 1980
Date: December 10, 1980 MAYORSCHICE
TO: MAYOR GEORGE LATIMER
FR: Thomas J. Kelley, Director, Department of Community Services
RE: General Construction of the Seal Island Display/Como Zoo
Administrative Order for Contract Change #G-1
Project #78-58C Contract L-8103-14
James Steele Construction Company
ACTION REQUESTED:
•
Approval of Administrative Order
•
PURPOSE AND RATIONALE FOR THIS ACTION:
Because of the poor quality and less than minimal thickness of
the existing concrete slab, it is necessary to place a supporting
element on top to establish a stable base from which to build upon.