BUDGET REVISION Date: i% /
AJ)MII'ISTRATI<'E ORDER,Consistent with the authority granted to the Mayor in Section 10.07.4 of the City Charter and
based on the request of the Director of the Department of Public Works
to amend the 19 86 budget of the Asphalt Paving Plant fund,the Director of the Department
of Finance and Management Services is authorized to amend said budget in the following manner:
Current Amended
Asphalt Paving Plant Budget Change Budget
12201-322-000 $ 309,000.00 ($2,500) $ 306,500.00
12201-898-000 -0- $2,500 $ 2,500.00
$309,000.00 $ 309,000.00
Explanation for Budget Revision
1. Under the approved 1985 budget a ventilation system was installed in the asphalt
plant operator control room. The installation cost was encumbered from the 1985
funds, but the engineering and inspection costs were not determined until recently.
This revision will allow these charges to be paid.
• 2. The current budget amount for code 322 is sufficient to allow this revision.
Prepared by:Activity Manager Approved by: yor/