CITY OF SAINT PAUL — OFFICE OF THE MAYOR
ADMINISTRATIVE ORDER FEB 2 - 1988
for
CONTRACT CHANGE AGREEMENT NO. 1
DUD! !P SO S COST.
� n,.y
ADMINISTRATIVE ORDER, Whereas, additions which proved to be necessary to the Improvement described
as SEVENTH—FRANK SEWER SEPARATION
known as ct EL-
#29003, City Project No.87—S-8032 Park Construction
Contractor, is composed of the following:
This change agreement work consists of the following items:
1. Addition of Reaney Street from Earl to Frank
2. Widen and change design on Atlantic, E. Seventh to Railroad
3. Additional items through Addendum #1
4. Additional concrete removal and replacement throughout the project
5. Extra asphalt work at Seventh and Earl
6. Addition of 40 sewer service reconnections on Seventh between Earl and Johnson
Parkway
• (See Attachment "Cost Summary of Change Order #1)
ORDERED, That the City of Saint Paul, through its Mayor, approves the foregoing additions made in ac-
cordance with the specifications in the sum of $ 118,533.52 said amount to be added to the lump sum con-
sideration named in the contract, known as RAcy #29003 , and which amount is to be financed from:
1987 CSSP Funding; no additional funding required.
A�OVED AS TO FORM
2 — lO 19 )(14,k t
Assistant ;ty Attorney Contractor
u ��a2. 19 .6)8 By et p
E ineer 7
Aari.644 19
•
Hea of ep t - finance r
Director of I Administrative Assistant to the Mayor