D3026 White - City Clerk CITY O F SAINT PA U L
Pink — Finance Dept.
Canary— Dept.
OFFIGF. OF THE MAYOR
• No: t./
ADMINISTRATIVE ORDER
Date: SEP 2 3 1976
ADMINISTRATIVE ORDER, In the matter of that certain contract known as Contract
No. L-7879 for a Bituminous Overlay of GEORGE STREET from Ohio St. to Concord St.
(Including the bridge at Robert Street), City Project No. 75-P-0474, Alexander
Construction Company, Contractor, the specified date of completion is July 15,
1976, and the Contractor did not complete the contract by said date of completion
because of delays caused by a labor strike, additional work, and coordination
problems, and it is hereby
ORDERED, That the City of Saint Paul, through its Mayor, extends the time of
completion to September 15, 1976, provided however, that this Order shall have
no force or effect unless the sureties on the Contractor's bond consent thereto
and file such consent in writing with the Head of the Finance Department of the
City of Saint Paul; and it is
FURTHER ORDERED, That the City of Saint Paul does not waive all claim for
liquidated damages and that engineering and inspection costs on this project
may be charged to the Contractor for such extended period.
APPROVED AS T,,Q FORM
Assistant Cit orn + "000l partmen Head
r7joseph F. Koenig, .W. Constriction Engineer
i
• �
Date
Administrative Assistant to Mayor
JFK/gs, 9/17/76