Loading...
D3011 White - City Clerk No. ,D 3®z Pink Finance Dept. gantry - Dept. Accounting Date SEP 2 1 1976 glue - Engineer Green - Contractor • CITY OF SAINT PAUL — OFFICE OF THE MAYOR ADMINISTRATIVE ORDER for CONTRACT CHANGE AGREEMENT NO. 2 ADMINISTRATIVE ORDER, Whereas, additions which proved to be necessary to the Improvement described as_ronstruction of the WHITE BEAR AVENUE BRIDGE NO. 62530 over the Chicago & Northwestern Company and Grading & Paving WTTTTF, REAR AVF:NtTF: from Case Avenue to Station 18+50 known as Contract L- 7700_JCity Project No. 74-B-1016 & 74-p-0488B, Cy-Con, Incorporated , Contractor, is composed of the following: Force Account work as listed on attached sheets 1, 2, and 3 $1,207.79 Class 4 granular backfill - see sheet 3 92.68 Water for dust control - see sheet 3 560.00 Salvage of topsoil - see sheet 3 3,008.17 Deduction in price of fence installed - see sheet 3 - 759.33 TOTAL CONTRACT CHANGE AGREEMENT NO. 2 $4,109.31 ORDERED, That the City of Saint Paul, through its Mayor, approves the foregoing additions made in ac- cordance with the specifications in the sum of $ 4,109.31 , said amount to be added to the lump sum con- sideration named in the contract, known as contract L-7700-1 , and which amount is to be financed from: No additional funds required, as the contract quantities underrun in cost by more than this amount. APPR VE AS FOR 19 iv' /."L. C Jngii i t Ci y o ey Contract 6r 197 By er fEngineer cad o t in c - �- `/v�'/ 1974 Director of ministrative Assistant to the Mayor JFK/gs, 2/3116 Attachments to Contract Change Agreement No. 2 page 2 of 3 WHITE BEAR AVENUE - 74-P-o488B & 74-B-1016 i FORCE ACCOUNT WORK 1976 (Continued) : April 26, 1976: Remove railroad manhole at the northeast corner of toe wall (not included in the original quantities). 930 loader @ 2 hr. each @ $15.73/hr. = $ 7.86 operator @ 2 hr. each @ 15.19/hr. = 7.60 laborer @ 2 hr. each @ 12.67/hr. = 6.34 $ 21.80 April 27. 1976: Remove debris from project site (not included in the original quantities) truck @ 12 hrs. each @ $ 9.50/hr. = $ 14.25 bobcat @ 2 hr. each @ 5.91/hr. = 2.96 laborer @ 3 hrs. each @ 12.67/hr. = 38.01 operator @ 2 hr. each @ 15.19/hr. = 7.6o truck driver @ 12 hrs. each @ 12.88/hr. = 19.32 82.14 • April 28, 1976: Add steps in manhole H2O (not included in original quantities). laborer @ 4 hrs. each @ $12.67/hr. = $ 50.68 generator @ 4 hrs. each @ 2.50/hr. = 10.00 hammer @ 4 hrs. each @ 1.09/hr. = 4.36 65-o4 April 29, 1976: Fine grade and dry class 5 in the cul-de-sac area disrupted as a result of water main adjustment. bobcat @ 4 hrs. each @ $ 5.91/hr. = $ 23.64 2 laborers @ 4 hrs. each @ 12.67/hr. = 101.36 operator @ 4 hrs. each @ 15.19/hr. = 60.76 185.76 April 30, 1976: Load & haul R.R. manhole (not included in original quantities). truck @ 1 hr. each @ $ 9.50/hr. = $ 9.50 loader @ 2 hr. each @ 15.73/hr• = 7.86 • driver @ 1 hr. each @ 12.88/hr. = 12.88 operator @ 2 hr. each @ 15.19/hr. = 7.60 37.84 page 1 of 3 Attachments to Contract Change Agreement No. 2 r Grading & Paving WHITE BEAR AVENUE - Case to Sta. 18+50 and WHITE BEAR AVENUE BRIDGE #62530 • City Project Nos. 74-P-0488B and 74-B-1016 Contract No. L-7700-1 Contractor - Cy-Con, Incorporated FORCE ACCOUNT WORK 1975: Force account work required during placement of catch basin lead C.B. #31 to M.H. #33 - Resulting from concrete pavement existing in trench area. August 22, 1975: 3 laborers @ 72 hrs. each @ $11.48/hr. = $258.30 foreman @ 2 hrs. each @ 15.40/hr. = 30.80 operator @ 72 hrs. each @ 13.16/hr. = 98.70 pickup @ 2 hrs. each @ 1.50/hr. = 3.00 5500 backhoe @ 72 hrs. each @ 8.08/hr. = 60.60 August 27, 1975: 2 laborers @ 12 hrs. each @ $11.48/hr. = $ 34.44 foreman @ 1 hr. each @ 15.40/hr. = 15.40 operator @ 12 hrs. each @ 13.16/hr. = 19.74 pickup @ 1 hr. each @ 1.50/hr. = 1.50 • 5500 backhoe @ 12 hrs. each @ 8.08/hr. = 12.12 97 ft. of pipe placed; whereas 200 lin. ft. should be placed in a 9 hour day; therefore efficiency of 97/200 = .485 or .515 lost ( .515) ( 534.60) _ $275.32 October 23, 1975: Remove extra footage of chain link fence required to slope existing ground to match the new roadway grades bobcat @ 2 hr. each @ $ 5.91/hr.. = $ 2.96 laborer @ 12 hrs. each @ 11.48/hr. = 17.22 operator @ 2 hr. each @ 15.19/hr. = 7.6o 27.78 FORCE ACCOUNT WORK 1976: April 26, 1976: Reshape area around cul-de-sac that was disrupted by the Water' Department resulting from water main elevation adjustment: John Deere @ 1 hr. each @ $11.98/hr. = $ 11.98 • 930 loader @ 2 hr. each @ 15.73/hr. = 7.86 laborer @ 1 hr. each @ 12.67/hr. = 12.67 operator @ 12 hrs. each @ 15.19/hr• = 22.78 55.29 I Attachments to Contract Change Agreement No. 2 page 3 of 3 WHITE BEAR AVENUE - 74-P-0488B & 74-B-1016 FORCE ACCOUNT WORK 1976 (Continued): May 1976 Construct 5 steps at 1117 White Bear, 3 steps at 1023 White Bear and burb wall at the northwest corner. of the retaining wall. All work required to match existing with new roadway grades. laborer @ 14.5 hrs. each @ $12.67/hr. _ $183.72 concrete @ 2.5 yds. each @ 28.00 x 1.15 = 80.50 lumber & materials @ 72.00 x 1.15 = 82.80 $ 347.02 TOTAL FORCE ACCOUNT WORK $1,097.99 Note - All hourly rates as listed above include 40% to cover the sub-contractor's overhead and various employee contributions (insurance, taxes, etc. ). Materials listed include 15% for handling. Contractor's 10% for administration, etc. 109.80 TOTAL $1,207.79 • ITEMS FOR WHICH PRICES ARE ESTABLISHED IN THE CONTRACT: Class 4 granular material for catch basin trench backfill - required because existing material was not suitable for backfill. 16.85 tons @ $5.50/ton (fixed unit price) 92.68 Water for dust control on project site 112 thousand gallons @ $5.00/thousand gallon 560.00 652.68 ITEMS FOR WHICH NEGOTIATED RATES WERE ESTABLISHED: Salvage Topsoil - material on the site was salbaged and used as topsoil 943 cu. yds. @ $3.19/cu. yds. 3,008.17 TOTAL ADDITIONS $4,868.64 DEDUCTION IN PRICE FOR USING SHORTER POSTS THAN SPECIFIED: 135 lin. ft. of H post (not used) @ $2.958/ft. $399.33 180 sleeves @ $2.00/sleeve (shorter sleeves used) 360.00 TOTAL DEDUCTION 759.33 TOTAL.ADDITIONAL AMOUNT $4,109.31 • Total Extra Work $4,868.64 Less Deduction of 759.33 Total Addition $4,109.31