D2976 Whitt3 - City Clerk No. �zz?je�
Pink - Finance Dept.
Canary - Dept. Accounting Date AUG 2 4 1976
Blue - Engineer
Green - Contractor
•
CITY OF SAINT PAUL — OFFICE OF THE MAYOR
ADMINISTRATIVE ORDER
for
CONTRACT CHANGE AGREEMENT NO. 1
ADMINISTRATIVE ORDER, Whereas, additions which proved to be necessary to the Improvement described
as Bituminous Overlay on PRIOR AVENUE N. from Ferona Ave. to Minnehahn Ave.
known as Contract L- 7874 , City Project No.-75--P--060, Total Asphalt Construction Comps
Contracts, is composed of the following:
Quantity Unit Price
3 Each Build 24" Side Inlet Opening @ $65.00 = $195.00
7 Lin. Ft. Rebuild Catch Basin @ $60.00 = $420.00
Total = $615.00
This work was required to better incorporate the improvement as planned with the
existing conditions.
Note that the unit price is established in the Fixed Unit Prices included in the
contract.
ORDERED, That the City of Saint Paul, through its Mayor, approves the foregoing additions made in ac-
cordance with the specifications in the sum of $615.00 said amount to be added to the lump sum con-
sideration named in the contract, known as contract L-7874 , and which amount is to be financed from:
Contract quantities have underrun. No additional funds are required.
PPR D S , FO
10 ig 96- clt
ssistant City Atto r ey Contractor
19 By .tC'i?cc�4
ngi e
19
Chief gineer Had ar ment Fin ph ce G
19�
Director of dministrative Assistant to the Mayor
JFK/gs, 8/11/76