ADMINISTRATIVE ORDER
Date: AUG 12 1976
i
ADMINISTRATIVE ORDER, In the matter of that certain contract known as Contract
No. L-7927 for Roadway Improvements in the WEST SEVENTH STREET COMMUNITY DEVELOPMENT
AREA YEAR 1, City Project No. 76-P-0632, Shafer Contracting Company, Inc. , Contractor,
the specified date of completion is August 1, 1976, and the Contractor did not complete
the contract by said date of completion because the municipal labor strike delayed the
start of the project and because, since the start of construction, extra work has been
added to the contract, and it is hereby
ORDERED, That the City of Saint Paul, through its Mayor, extends the time of completion
to September 1, 1976, provided however, that this Order shall have no force or effect
unless the sureties on the Contractor's bond consent thereto and file such consent in
writing with the Head of the Finance Department of the City of Saint Paul; and it is
FURTHER ORDERED, That the City of Saint Paul hereby waives all claim for liquidated
damages and that no engineering and inspection costs on this project will be charged
to the Contractor for such extended period.
•