ADMINISTRATIVE ORDER,In the matter of that certain contract known as Contract
No. L-7928 for Roadway Improvements in the THOMAS-DALE COMMUNITY DEVELOPMENT AREA
YEAR 1 and AVON-VICTORIA-ST. ANTHONY HILL STORM SEWER SYSTEM, City Project Nos.
76-P-0634 and 76-5-1583, Shafer Contracting Company, Inc. , Contractor, the
specified date of completion is August 1, 1976, and the Contractor did not complete
the contract by said date of completion because the municipal employees labor strike
delayed the start of the project and because extra quantities have been added to the
contract, and it is hereby
ORDERED, That the City of Saint Paul, through its Mayor, extends the time of
completion to August 20, 1976, provided however, that this Order shall have no
force or effect unless the sureties on the Contractor's bond consent thereto and
file such consent in writing with the Head of the Finance Department of the City
of Saint Paul; and it is
FURTHER ORDERED, That the City of Saint Paul hereby waives all claim for liquidated
damages and that no engineering and inspection costs on this project will be charged
to the Contractor for such extended period.
•
APP S TO Fj M
Assists City Attorney r7grtment Head
Joseph F. Koenig ` P.W. Constr ction Engineer
Date
Administrative Assistant to Mayor
JFK/gs, 8/4/76