ADMINISTRATIVE ORDER, In the matter of that certain contract known as Contract
No. L-7926 for LEXINGTON-HAMLINE COMMUNITY DEVELOPMENT YEAR 1, City Project No.
76-P-0648, Ashbach Construction Company, Contractor, the specified date of completion
is July 13, 1976, and the Contractor did not complete the contract by said date of
completion because of the municipal employee strike, because of diseased tree removals,
and because of the desire to place sod late in July or early August, and it is hereby
ORDERED, That the City of Saint Paul, through its Mayor, extends the time of completion
to August 15, 1976, provided however, that this Order shall have no force or effect
unless the sureties on the Contractor's bond consent thereto and file such consent in
writing with the Head of the Finance Department of the City of Saint Paul; and it is
FURTHER ORDERED, That the City of Saint Paul hereby waives all claim for liquidated
damages and that no engineering and inspection costs on this project will be charged
to the Contractor for such extended period.