D2821 White - city Clerk CITY O F SAINT PA U L
Pink — Finance Dept.
Canary- Dept.
OFFICE OF THE MAYOR
No: U
ADMINISTRATIVE ORDER JUN 16 1976
Date:
•
ADMINISTRATIVE ORDER, In the matter of that certain contract known as Contract
No. L-7709 for the ST. ANTHONY PARK STORM SYSTEM, City Project No. 74-5-0460B1,B2,C,
Acton-McCrossan/Joint Venture, Contractor, the specified date of completion is
July 1, 1976, and the contractor will not complete the contract by said date of
completion because of the 1975 construction labor strike and work suspension by the
Department of Labor and Industry due to a fatal accident, and it is hereby
ORDERED, That the City of Saint Paul, through its Mayor, extends the time of
completion to August 6, 1976, provided however, that this Order shall have no
force or effect unless the sureties on the Contractor's bond consent thereto and
file such consent in writing with the Head of the Finance Department of the City
of Saint Paul; and it is
FURTHER ORDERED, That the City of Saint Paul hereby waives all claim for liquidated
damages and that no engineering and inspection costs on this project will be charged
to the Contractor for such extended period.
APPROVED AS TO OR
3 y
As tint kqtor e artment Head �
�odep 5'�F lKoenig P.W. Const uction Engineer
fate
Administrative Assistant to Mayor
JFK/gs-6/4/76