D2577 White - City Clerk CITY OF SAINT PAUL
Pink — Finance Dept.
Canary— Dept.
OFFICE OF THE MAYOR
No: r
ADMINISTRATIVE ORDER
Date: FEB 5 1976
ADMINISTRATIVE ORDER, In the matter of that certain contract known as Contract
No. L-7826 for the JEFFERSON-WHEELER STORM SEWER SYSTEM, City Project No. 75-S-1493,
Shafer Contracting Company, Inc. , Contractor, the specified date of completion is
December 11, 1975, and the Contractor did not complete the contract by said date of
completion because of a labor strike, and it is hereby
ORDERED, That the City of Saint Paul, through its Mayor, extends the time of
completion to June 15, 1976, provided however, that this Order shall have no force
or effect unless the sureties on the Contractor's bond consent thereto and file
such consent in writing with the Head of the Finance Department of the City of
Saint Paul; and it is
FURTHER ORDERED, That the City of Saint Paul hereby waives all claim for liquidated
damages and that no engineering and inspection costs on this project will be charged
to the Contractor for such extended period.
APPROVED TO FORM
Assi t City torney elbartment Head
Joseph F. Koenig, P.W. Con ruction Engineer
r
Date
Administrative Assistant to Mayor
JFK/gs, 1/27/76