ADMINISTRATIVE ORDER, In the matter of that certain contract known as Contract
No. L-7751 for CLEVELAND AVENUE BRIDGE No. 62528 over C.M.St.P.& P.R.R.Co.(Ford Spur)
City Project No. B 1033, Northern Contracting Company, Contractor, the specified date
of completion is August 27, 1975, and the Contractor did not complete the contract by
said date of completion because of coordination problems involving sub-contractors
who had a backlog of work caused by various labor strikes, and it is hereby
ORDERED, That the City of Saint Paul, through its Mayor, extends the time of completion
to September 12, 1975, provided however, that this Order shall have no force or effect
unless the sureties on the Contractor's bond consent thereto and file such consent in
writing with the Head of the Finance Department of the City of Saint Paul; and it is
FURTHER ORDERED, That the City of Saint Paul claim liquidated damages per
Paragraph A-7.7 of the Special Provisions of the Specifications from August 28, 1975,
thru September 1, 1975, and it is
FURTHER ORDERED, That the Contractor be charged for field engineering and inspection
costs involved on this project from September 4 , 1975, thru September 12, 1975•