ADMINISTRATIVE ORDER 0CT 2 1975
Date:
ADMINISTRATIVE ORDER, In the matter of that certain contract known as Contract
No. L-7859 for the Bituminous Overlay of WALL STREET between Kellogg Boulevard and
Seventh Street, City Project No. 75-P-0501, Tower Asphalt, Inc. , Contractor, the
specified date of completion is September 1, 1975, and the Contractor did not
complete the contract by said date of completion because the contract was not
countersigned in time to allow the Contractor the specified fifteen working days
prior to the September 1,, 1975 completion date, and it is hereby
ORDERED, That the City of Saint Paul through its Mayor, extends the time of completion
to September 9, 1975, provided however, that this Order shall have no force or effect
unless the sureties on the Contractor's bond consent thereto and file such consent in
writing with the Head of the Finance Department of the City of Saint Paul; and it is
FURTHER ORDERED, That the City of Saint Paul hereby waives all claim for liquidated
damages and that no engineering and inspection costs on this project will be charged
to the Contractor for such extended period.
•
APPROVE AS O FOR
As ant ty tt ey Department Head
� ,oseph F. Koenig, P.W. Construction Engineer
Date
Admin' ra ve istant to Mayor
JFK/gs, 9/22/75