Loading...
D1876 White — City Clerk No. 0 _ ,z"r zb Pink — Finance Dept. Canary — Dept. Accounting Date January 27, 1975 Blue — Engineer Green — Contractor • CITY OF SAINT PAUL — OFFICE OF THE MAYOR ADMINISTRATIVE ORDER for CONTRACT CHANGE AGREEMENT NO. 1 ADMINISTRATIVE ORDER, Whereas, additions which proved to be necessary to the Improvement described as construction of Bridge No. 62528 to carry CLEVELAND AVENUE over the tracks of the C.M.St.P. & P. R.R. Co. known as Contract L- 7751 , City Project No.B-1033 Northern Contracting Company, , Contractor, is composed of the following: During class "R" footing excavation for the north abutment, ground water slowly infiltrated into the footing area. Since water is detrimental to shale and causes swelling, it was necessary to raise the footing elevation 1.5 feet and place a 6 inch concrete seal (1A43 Concrete) below the concrete footing. It was mutually agreed that the contract quantities should be changed and payment adjusted as follows: Increase or Specifi- Item uantity Unit Contract (+) Amount Decrease cation No. Unit Price Decrease 2401-501 onc., Mix No. 3Y43 10.0 Cu.Yd. $120.00 - $1,20 0.00 Decrease 2401.501 one. , Mix No. 1A43 2.0 Cu.Yd. 65.00 - 130.00 Decrease 2401.521 tructural Excavation, lass "R" 41.0 Cu.Yd. 20.00 - 820.00 Increase 2401.501 onc. , Mix No. 1A43 30.0 Cu.Yd. 65.00 + 1,950.00 Decrease Estimate Cost of Contract by Amount 200.00 changes ORDERED, That the City of Sdaint Paul, through its Mayor, approves the foregoing i s made in ac- cordance with the specifications jacthe sum of $200.00 deducted p � to be to the lump sum con- sideration named in the contract, known as contract L- 7751 , APP 0 D TO F M 19 A Wnt Att y Contr / /Z? 19 Z f B Ergine7erl f '�' Q tv toe Engin r Head o ent of in e � O 19 76- 4 Director of A16inistrative"Assl6ta nt to the Mayor