D1663 Wh�ft`e — City Clerk No.
Pink — Finance Dept. QJ 114
Canary — Dept. Accounting Date
Blue Engineer
Green — Contractor
•
CITY OF SAINT PAUL — OFFICE OF THE MAYOR
ADMINISTRATIVE ORDER
for
CONTRACT CHANGE AGREEMENT NO. 1
ADMINISTRATIVE ORDER, Whereas, additions which proved to be necessary to the Improvement described
as Grading. Surfacing and Construction of Concrete Curb and Gutter on JENKS AVENUE
from Pa=p Avenue tn 't 9Q' West
,
known as Contract L-776?, City Project No. 4-G-2011, Total Asphalt Construction Company ,
Contractor, is composed of the following:
See attachment.
Total Additions $373.00
Total Deduction 75.00
Net Addition $298.00
•
ORDERED, That the City of Saint Paul, through its Mayor, approves the foregoing additions made in ac-
cordance with the specifications in the sum of $298.00 said amount to be added to the lump sum con-
sideration named in the contract, known as contract L- 7762 and which amount is to be financed from:
Public Improvement Aid 09050-465.
APPROVED AS TO FORM
19 TOTAL ASPHALT CONSTRUCTION CO
sistant 'ty A Contractor
d !J 19 !V By czx) t
ngi
— - 19
Ch' ngineer Head of De artm nt of Finance L
1924—
it ctor of Admi istrative Assi tant o the Mayor
r
• Attachment to Administrative Order
for
Contract Change Agreement No. 1
JENKS AVENUE - Payne to 120' West
Contract No. L-7762 City Project No. 74-G-2011
Contractor - Total Asphlat Construction Company
ADDITIONS:
1. Adjust four water gate valves which were not
shown on the plans and were not known to exist.
Adjust gate valve 4 each @ $45.00 = $180.00
2. Remove 4" concrete walk to allow for construction
of a pedestrian ramp. This removal was not
included in the lump sum bid for the contract.
Remove monolithic concrete walk - 12 sq. yds. @ 1.50 = 12.00
3. Construct 4" concrete walk for a pedestrian ramp.
This item was not included in the lump sum bid
for the contract.
Construct 4" concrete walk 181 sq. ft. @ 1.00 = 181.00
Total Additions = $373.00
DEDUCTION:
Concrete driveway not constructed.
This reduction was due to poor workmanship.
6" concrete drive 7.5 sq. yds. @ $10.00 = $ 75.00
Total Deduction = $ 75.00
NET TOTAL ADDITION = $298.00
•