ADMINISTRATIVE ORDER
Date: NOV N ��
ADMINISTRATIVE ORDER, In the matter of that certain contract known as Contract
L-7762 for the Grading and Surfacing of LUELLA STREET & JENKS AVENUE, City Project No.
74-G-2031 and G-2011, Total Asphalt Construction Company, Contractor, the specified
date of completion is August 1, 1974, and
WHEREAS, The Contractor did not complete the project by said completion date because
the contract was not counter-signed until September 5, 1974, it is hereby
ORDERED, That the proper City Officials are hereby authorized and directed to execute
an amendment to said contract extending the time of completion to October 30, 1974,
provided however, that this Order shall have no force or effect unless the sureties
on the Contractor's bond consent thereto and file such consent in writing with the
Head of the Finance Department of the City of Saint Paul; and it is
FURTHER ORDERED, That the City of Saint Paul hereby waives all claim for liquidated
damages and that no engineering and inspection costs on this project will be charged
to the Contractor for such extended period.
•
APPROVED AS T FORM
�Q �ciC y
Assistant City Attorney Department Head
Yeoseph F. Koenig, P.W. Constr4tion Engineer
Date
Administr 'a As nt o Mayor