D1494 White — City Clerk CITY O F SAINT PAUL
Pink — Finance Dept. No:
Canary— Dept.
OFFICE OF THE MAYOR Date: AUG 2 0 1974
ADMINISTRATIVE ORDER
•
ADMINISTRATIVE ORDER, In the matter of that certain contract known as Contract No.
1-7660 for the MARYLAND-GALTIER RELIEF SEWER, City Project No. 73-S-0998, McDonald &
Associates, Inc. , Contractor, the specified date of completion is July 15, 1971 , and
the Contractor did not complete the contract by said date of completion because an
easement acquisition was not completed prior to award of the contract, and it is
hereby
ORDERED, That the City of Saint Paul, through its Mayor, extends the time of completion
to August 9, 1974, provided however, that this Order shall have no force or effect
unless the sureties on the Contractor's bond consent thereto and file such consent in
writing with the Head of the Finance Department of the City of Saint Paul; and it is
FURTHER ORDERED, That the City of Saint Paul hereby waives all claim for liquidated
damages and that no engineering and inspection costs on this project will be charged
to the Contractor for such extended period.
•