Date
ADMINISTRATIVE ORDER
ADMINISTRATIVE ORDER, In the matter of Contract L-7607 for the construction
of the WESTERN AVENUE STAIRWAY between Ramsey Street and Irvine Avenue, City
Project No. B-1038, First Minnesota Construction Company, contractor, the
specified date of completion is June 1, 1973, extended to September 1, 1973) by
Administrative Order No. D-800, and due to late receipt of materials caused by
the Contractor's scheduling, the Contractor was not able to complete the contract
by said date of completion, it is hereby
ORDERED, That the City of Saint Paul, through its Mayor extends the time of
completion to December 13, 1973, provided, however, that this order shall have
no force or effect unless the sureties on the Contractor's bond consent thereto
and file such consent in writing with the Director of Finance and Management
Services of the City of Saint Paul; and it is
FURTHER ORDERED, that Engineering and Inspection Costs will be charged to the
Contractor for such extended period.