ADMINISTRATIVE ORDER, In the matter of that certain contract known as Contract No.
L-7647, Storm Sewers at Various Locations: CALIFORNIA AVENUE & WHITE BEAR AVENUE
STORM SEWER (Project No. 73-S-1507), CONWAY STREET STORM SEWER (Project No. 73-S-1508),
FOREST STREET & WAKEFIELD AVENUE STORM SEWER (Project No. 73-S-11+86) , and NEBRASKA
AVENUE & MC AFEE STREET STORM SEWER (Project No. 73-S-1499) , Maplewood Sewer and Water,
Inc. , Contractor, the specified date of completion was September 1, 1973, and the
Contractor did not complete the contract by said date of completion, it is hereby
ORDERED, That the City of Saint Paul, through its Mayor, extends the time of completion
to October 15, 1973 to coincide with the actual construction completion, provided
however, that this Order shall have no force or effect unless the sureties on the
Contractor's bond consent thereto and file such consent in writing with the Head of
the Finance Department of the City of St. Paul; and it is
FURTHER ORDERED, That the City of Saint Paul hereby waives all claim for liquidated
damages and that no engineering and inspection costs on this project will be charged
to the Contractor for such extended period.