OFFIGE OF THE MAYOR
Date: JUN 26 1973V
ADMINISTRATIVE ORDER
ADMINISTRATIVE ORDER, In the matter of that certain contract formerly known as
Comptroller's Contract L-75 +3 for the PEDERSEN-THIRD RELIEF SEWER SYSTEM, City
Project No. 72r-S-1434, Peter Lametti Construction Company, Contractor, the speci-
fied date of cim►pletion is December 1, 1972, and for reasons beyond the Contractor's
control he was; not able to complete the contract by said date of completion, it is
hereby
ORDERED, That the City of Saint Paul, through its Mayor, extends the time of comple-
tion to June 30, 1973, provided however, that this Order shall have no force of
effect unless the sureties on the Contractor's bond consent thereto and file such
consent in writing with the Head of the Finance Department of the City of Saint Paul;
and it is
FURTHER ORDERED, That the City of Saint Paul hereby waives all claim for liquidated
damages and that no engineering and inspection costs on this project will be charged
to the Contractor for such extended period.
k APPROVED AS TO FUNDING
f
Director, Department of Finance
APPROVED AS FOR and Management Services
I tant Vy or y T epartrnTnTTfeea
c
Joseph F. Koen g, Construct on Engin
be
Admini tive sis to Mayor