CITY OF SAINT PAUL — OFFICE OF THE MAYOR
ADMINISTRATIVE ORDER
for
CONTRACT CHANGE AGREEMENT NO. 3
ADMINISTRATIVE ORDER, Whereas, additions which proved to be necessary to the Improvement described
as Site Work at Conway.Heights
known as Contract L- 7483 , City Project No. 71-43_ Robert O. Westlund, Genl. Contr.
Contractor, is composed of the following:
1. Repair boulevard, as needed. from parking lot West to East to corner of
property line, Conway St. Also from parking lot next to library up to where
sewer from Wilson St. has been brought in.
2. One roll of sod along each side of sidewalk, seed & mulch the rest.
3. Build, a iise along South side of tennis courts to prevent water from crossing
courts, sod as necessary.
4. Install 1� 10-inch posts as directed by Architect on site.
TOTAL EXTRA: $2, 335
ORDERED, That the City of Saint Paul, through its Mayor, approves the foregoing additions made in ac-
cordance with the specifications in the sum of $ 2, 335. 00 said amount to be added to the lump sum con-
sideration named in the contract, known as contract L- 7483 , and which amount is to be financed from:
93771-460-009
OVED AS TO R
S.g 19 ' Robert O. Westlund. General Contractor
S' City At Contractor
see letter dated. April 25, 1973
✓� 19 7� By
x Asst.
1 -.7 _ 19
C ' Head of ent of Finance
19 7 -3
irector of Community inistrative As st o tfie Mayor
Services Dept. 0