CITY OF SAINT PAUL - OFFICE OF THE MAYOR
ADMINISTRATIVE ORDER
for
CONTRACT CHANGE AGREEMENT NO. G-1
ADMINISTRATIVE ORDER, Whereas, additions which proved to be necessary to the Improvement described
as General Construction of Fire Training Tower and Pump Test Pit
known as Contract L-7613 , City Project No. 69-83 James Steele Construction Co.
Contractor, is composed of the following:
1. Excavate approximately 1, 200 c. y. of unsuitable fill
material which was placed under location of training tower
foundation @ $. 80 per cubic yard. . . . . . . $ 960. 00
2. Move, place and properly compact approximately
1, 200 c. y. of suitable granular material under
location of training tower foundation @ $1. 98 . . . . . . 2, 376. 00
Total ADD $3, 336. 00
ORDERED, That the City of Saint Paul, through its Mayor, approves the foregoing additions made in ac-
cordance with the specifications in the sum of $ said amount to be added to the lump sum con-
sideration named in the contract, known as contract L- 7613 , and which amount is to be financed from:
94071-460-007
A VED AS TO RM
y G 19 ?3 James Steele Construction Co.
t City r y Contractor
197;�— By (Unit prices specified in orig. specificatioi
Asst. City Arch.
19
Head of Department of Finance
Direc or of Administrative Assist t to ayor
�� � Fire D pt.