OFFICE OF THE MAYOR Date: LIAR 1 91973
ADMINISTRATIVE ORDER
•
ADMINISTRATIVE ORDER, In the matter of Finance Department-Accounting Division
Contract No. 1.-7584-1, namely, Electrical Construction For the Watermain at Como
Golf Course, between the City of St. Paul and Batzli Electric Company-Electrical
Contractor, the specified date of completion is December 15, 1972, and
Due to a delay in the shipment of construction materials the Electrical
Contractor wal� unable to complete the project by the specified date of
December 15, 1972
the
Ordered that/proper city officials 4& extend the time of completion to
April 15, 1973, and, provided however, that this Order shall have no force or
effect unless the sureties on the Contractor's bond consent thereto and file such
consent in wr ting with the Finance Department - Accounting Division, and be it
• Furt er Ordered, That the City of Saint Paul hereby makes no 2li3t=r
claim for liquidated damages or engineering and inspection costs on this project
against the Contractor for such extended period.
Robert W. Trudeau
Director
Department of Finance and Management
Services 77