D402 White — City Clerk No. D =- L
Pinks — Finance Dept. �A� 2 619T3
Canary — Dept. Accounting Date
Blue — Engineer
Greer — Contractor
• CITY OF SAINT PAUL — OFFICE OF THE MAYOR
ADMINISTRATIVE ORDER
for
CONTRACT CHANGE AGREEMENT NO._ 1
ADMINISTRATIVE ORDER, Whereas, additions which proved to be necessary to the Improvement described
as MARIA THIRD STORM SEWER SYSTEM
known as Contract L- 7524 , City Project No. 72-5-1438A, F. Morettini Construction Come
Contractor, is composed of the following:
As per attached sheet.
Total Deductions from Contract $30,250.00
Total Additions to Contract 7,780.00
TOTAL NET DEDUCTION FROM CONTRACT $22,470.00
•
ORDERED, That the City of Saint Paul, through its Mayor, approves the foregoing additions made in ac-
deducted from
cordance with the specifications in the sum of $ 22.470.00 said amount to be qodmb= the lump sum con-
sideration named in the contract, known as contract L-7524 and ...,ieh ° nt is be aaneed
APPROVE AS TO FORM
�A Q�6t - — 19 fail rtA;
AssistaF1_qqttP&e0 Contrac or
y
Ict 19_ By G
• _ �_ 19
eer Head of Department of Finance
'z 19 ZI Fh 3
Director of Ader6istrative AssistAnt to th Mayor
1
i
• Attachment to
ADMINISTRATIVE ORDER FOR CONTRACT CHANGE AGREEMENT NO. I
MARIA-THIRD STORM SEWER SYSTEM
City Project No. 72-S-1438A
Contract No. L-7524
Contractor - F. Morettini Construction Company
DEDUCTIONS FROM CONTRACT
Type 7A catch basin 1 each @ $500.00 = $ 500.00
Type 10A catch basin 1 each @ 400.00 = 400.00
Street Restoration lump sum 29,350.00 = 29,350.00
Total Deductions = $30,250.00
ADDITIONS TO CONTRACT
Type IV Manhole 5 each @ $500.00 = $2,500.00
�L'ype lA Catch Basin 1 each @ 300.00 = 300.00
Type 3C Catch Basin 3 each @ 225.00 = 675.00
Manhole opening (1303) 4 each @ 100.00 = 1+00.00
• Manhole opening (1302) 8 each @ 50.00 = 400.00
Remove Catch Basin 3 each @ 60.00 = 180.00
Reconstruct Catch Basin 6 lin. ft. @ 50.00 = 300.00
Sewer Service Connection 1 each @ 250.00 250.00
Remove Monolithic Walk 93 sq. yd. @ 1.00 = 93.00
Remove Concrete Curb 201 lin. ft. @ .75 150.75
Construct 4" Monolithic Walk 834 sq. ft. @ 1.00 = 831+.00
Construct Concrete Curb 201 lin. ft. @ 1+.00 = 801 .00
Construct Support Piers 2.5 cu. yd. @ 50.00 = 125.00
Subgrade Excavation 105 cu. yd. @ 1.50 = 157.50
Trench Excavation 39.5 cu. yd. @ 3.50 = 138.25
Gravel Base (Class u) 105 cu. yd. @ 4.50 = 472.50
$ 7,780.00
TOTAL NET DEDUCTION FROM CONTRACT = $22,470.00