D297 White - City Clerk No 0 l Pink - Finance Dept. Canary - Dept. Accounting (Dick Scott, Rm. 545) Date Blue - Engineer NO 2 Green - Contractor CHANGE ORDER MSM-3 CITY OF SAINT PAUL — OFFICE OF THE MAYOR ADMINISTRATIVE ORDER for CONTRACT CHANGE AGREEMENT N0. MSM-3 ADMINISTRATIVE ORDER, Whereas, additions which proved to be necessary to the Improvement described as Mechanical Sheet Metal Work of the Saint Paul Civic Center Multi-Purpose Arena Building. known as Contract L- 7345, City Project No. 70-45 Como Specialty Co. Contractor, is composed of the following: 1. Provide and install replacement fractional horsepower electric motors for power roof ventilators #21 and #43 $154. 00 Z. Provide 16 galvanized iron drip pans for pumps on eight air handling platforms in truss space. 138. 00 Total $292. 00 • -per Civic Center Authority Resolution #523 and Project Architect's change order #MSM-3 ORDERED, That the City of Saint Paul, through its Mayor, approves the foregoing additions made in ac- cordance with the specifications in the sum of $ 292. 00 said amount to be added to the lump sum con- sideration named in the contract, known as contract L- 7345 , and which amount is to be financed from: 7420-460 APPROVED AS TO FORM 1194 ';7 Como Specialty Co. As it City Att a Contractor:.;:_ ' ;;_; T w. TP" ' 19_, By see attAched 6hange order #MSM-3 - - - 19 . Chie Head of De tment_af-F' ance !� ` 19 J. ector of Administrative Assist to Ke Mayor