OFFICE OF THE MAYOR
Date: OCT 2 1972 72�
ADMINISTRATIVE ORDER
ADMINISTRATIVE ORDER, In the matter of that certain contract formerly known as
Comptroller's Contract L-7374-1 for Grading and Surfacing ALBERT STREET from
Jessamine Avenue to Brewster Street, BREWSTER STREET from Snelling Avenue to Albert
Street, JESSAMINE AVENUE from Albert Street to Hamline Avenue, also construction of
a storm and sanitary sewer, City Project Nos. 71-G-1821 and 71-S-1299B, Arcon
Construction Company, Inc., Contractor, the specified date of completion is July 15,
1972, and for reasons beyond the Contractor's control he was not able to complete
the contract by said date of completion, it is hereby
ORDERED, That the City of Saint Paul, through its Mayor, extends the time of comple-
tion to September 22, 1972, provided however, that this Order shall have no force or
effect unless the sureties on the Contractor's bond consent thereto and file such
consent in writing with the Head of the Finance Department of the City of St. Paul;
and it is
FURTHER ORDERED, That the City of Saint Paul hereby waives all claim for liquidated
damages and that no engineering and inspection costs on this project will be charged
to the Contractor for such extended period.