ADMINISTRATIVE ORDER, In the matter of that certain contract formerly known
as Comptroller's Contract L-7348, for .Grading, Surfacing and.Constructing Concrete
Curb and Gutter on FOXRIDGE ROAD, .PARKLAND COURT, V'ALLEYSIDE DRIVE', WAPLER LANE, and
also Construct the BATTLE CREEK WEST SEWER SYSTEM, City Project Nos. '70-G-1952 and
70-S-1416, Robert W. Moore Company, Contractor, .the...specified date of completion is
August 1, 1971, and for reasons beyond the Contractor's control he was not able to
- .complete.'the contract by said date of completion, it is hereby ' '.
ORDERED, That the City of Saint Paul, through its Mayor, 'extends the •time of
completion to August 15, 1972, provided however, .that this. 'Order shall have no force
or effect unless the sureties on the Contractor's bond consent thereto and file such
consent in writing with the Head of the Finance Department of the City of .Saint Paul;
and it is
FURTHER' ORDERED, That the City.of Saint Paul hereby waives .all' claim for liquidated
damages and that no engineering and inspection costs on this project will be charged to
the Contractor for such extended period.