177839 Original to rty Clerk 1 819
CITY OF ST. PAUL
COUNCIL NO. - 1.1? gall
OFFICE OF THE CITY CLERK
CO CIL RESOLUTION—GENERAL FORM
PRESENTED BY /3,
COMMISSIONER DATF
RESOLVED, That an extension of time until June 1, 1956,
be allowed for completion of contract number G-1 between
the City of Saint Paul and the Standard Stone Company,
said contract for the Installation of Sidewalks and
Curbing for a Playground Area located on Dale Street,
and said extension being necessitated due to inclement
weather conditions.
•
council File No. 1778.19-gy Bernard
T. Holland—
until R alp t ann extension of time
com-
pletion of contract number d for tWeen the City of Sait Paul nd the
Standard Stone Company,said contract
Cu'U fee a p installation Area boat Street. and said extension
*�s�gitated due to incle,aient.l
A¢oyrfed bebyy the(7o'ur+elt 6y
red"ltfey 1S, ll88.
agar l8, MS)
MAY 151956
COUNC EN Adopted by the Council 195_
Yeas Nays
Gibbons M4114 5
pproved 195_
.
%Ithlli L n Favor /.4 L
nson Mayor
fffeterson ainst
r.President, Dillon
1111
5M 6-55 aleP02
17Duplicate to Printer
839
CITY OF ST. PAUL FOLENCIL NO.
OFFICE OF THE CITY CLERK
COUNCIL RESOLUTION—GENERAL FORM
PRESENTED BY
COMMISSIONER DATF
RESOLVED, That an extension of time until June 1, 1956,
be allowed for completion of contract number G-1 between
the City of Saint Paul and the Standard Stone Company,
said contract for the Installation of Sidewalks and
Curbing for a Playground Area located on Dale Street,
and said extension being necessitated due to inclement
weather conditions.
of 151956
56
COUNCILMEN Adopted by the Council 195_
Yeas Nays ;"
Gibbons
Halvorson Approved 195—
Holland
Marzitelli Tn Favor
Mortinson Mayor
Peterson 9 Against
Mr. President, Dillon
5M 6-55 4Er*°2
ROBERT A. LOBDELL
Director of Public Recreation
W. LA MONT KAUFMAN ALFRED H. SCHROEDER
Supt. of Parks ERNEST W. JOHNSON City Architect
Consultant in Public Recreation
CITY OF SAINT PAUL ` " �7 fi� ((��
Capital of Minnesota
DEPARTMENT OF
PARKS, PLAYGROUNDS AND PUBLIC BUILDINGS
445 City Hall, Zone 2
BERNARD T. HOLLAND, Commissioner
ARTHUR F. COLEMAN, Deputy Commissioner
May 15, 1956
Comsr. Bernard T. Holland
Dept. Parks, Playgrounds & Public Bldgs.
Dear Sir:
Contract Number G-1 was awarded to the Standard Stone
Company for the Installation of Sidewalks and Curbing for
a Playground Area located on Dale Street.
The contract documents call for a completion date of
May 10, 1956; however, due to inclement weather conditions
and conditions beyond the control of the contractor, the
contractor has requested an extension of time until June
1, 1956, for completion of this contract.
This is a reasonable request, and it is therefore
recommended that an extension of time be granted to the
Standard Stone Company as requested.
Very truly yours
Al ,ed H. Schroeder
Architect
AHS :al
ccts Storey
Schnarr