Loading...
184005 File No. 184005—By Frank D. ! 1 P y Original to City Clerk • A itelli— 7 f `�j CITY OF ST. PAI No.s55IS-465,nComptrol eth Con-L CJ No. L-5655, dated September 14, NO. • OFFICE OF THE CIT``for the construction of the Trout Sewer Extension to Rice Street, OUNCIL RESOLUTION `orett ni, Contractor, due to un- �e �undation and sub-soil con- / t di c1 sed by the borings/ PRESENTED BY /,� ��// hit 'ndirated COMMISSIONE L«/_ -�� `L� ti- rya 'y p c jir WHEREAS, in connection with Contract No. 55-S-465, Comptroller' s Contract No. L-5655, dated September 1 ., 1955, for the construction of the Trout Brook Sewer Extension to Rice Street, F. Morettini, Contractor, due to unsuitable foundation and sub-soil conditions not disclosed by the borings taken in advance but indicated by test pilings driven during the progress of the work, it was necessary to order the contractor to perform extra work in driving piling and placing concrete foundations and doing incidental work for an additional 686 feet of the 8' diameter reinforced concrete pipe sewer, such additions being specifically provided for in the general specifications and in special provisions under the fol1owi.nr- clause: "The Engineer reserves the right to increase or decrease the amount of piling and to order piling driven .-here not shown on the plan" and a separate unit price for additional pilings being called for In the bid and not included in the lump sum price; and WHEREAS, a. work order was iss ued on February 27, 1956, by the Depart- ment of Public Works for such additional work with the provision that the final additional cost be based on the actual auantities of work involved; and WHEREAS, Such final cuantities of work has been determined and the cost arrived at on the basis of the fixed schedule of prices in the contract for excavation, gravel sub base, steel and wood pilings and in accordance with an agreed price per cubic yard. for class A concrete and. class C concrete as provided for in the general specifications of the contract, the Quantities and cost amount being as follows: Excavation - including extra. depth andilt Om trench width and side slopes ' Above 12' depth 3126 cu. yds $3.00 (schedule price) $9,378.00 Below 12' depth 775 cu. yds. $3.50 (schedule price) 2,712.50 Piling - 10,350 lin. ft. @ $2.25 (bid price) 23,287.50 Gravel Sub Base - 58.5 cu. yds. @ P6.,00 (S%hedule price) 351.00 Concrete Slab Class A concrete 548 cu. yds. @ $45.00 (agreed price) 24,660.00 Concrete saddle Class C concrete 395cu. ids. $30.00 (agreed ") 11,850.00 Reinforcing Steel 26132# @ 0.12 (schedu2 nrice) 3,135.84 COUNCILMEN midopte(d by 3t e�Council $75,3744 4 Yeas Nays A nnrnved 195— . !84O( 5 Original to City Clerk CITY OF ST. PAUL COLENCIL NO. OFFICE OF THE CITY CLERK COUNCIL RESOLUTION—GENERAL FORM PRESENTED BY COMMISSIONER DATF WHEREAS, under date of September 22, 1956, the said Contractor filed with this Council a statement in writing claiming that the addition to the contract for the extra work under the contract Change Order for reim- bursement to it for the work performed, should be in the sum of $158,692.39, and thereafter said Contractor later amended said figure to $881901.00 by affidavit executed July 6, 1957, attached to which was an itemization of its asserted costs in connection with the extra work; and WHEREAS, as heretofore stated, the Department of Public Works has determined that the net total additions to the contract should be in the sum of 875,374.84, covering the items listed herein by separate category and in the specific amounts expressly set forth; therefore, be it RESOLVED, that the Council of the City of Saint Paul does hereby approve and authorize the foregoing additions to said project and contract made in accordance with the specifications, in the sum of 05,374.84, said sum to be added to the lump sum consideration set out in the contract, described as Comptroller's Contract No. L-5655, and that the said sum be authorized as payment in full of the claim heretofore filed with this body by the said Contractor, and the Department of Public Works, through its Commissioner, having agreed with the Contractor that the amount of $75,374.84 is a reasonable amount to be added to the above contract for the extra work done under and pursuant to the contract Change Order of February 27, 1956, said amount shall be paid to the said Contractor upon the execution by Contractor of proper releases to the City of Saint Paul for all and every claim or claims of said Contractor arising from the carrying out of the above improvement. AUG 2 'psi ()- COUNCILMEN Adopted by the Council —195— Yeas Nays DeCourcy AUG 2 9957 Holland t Approved 195— Marzitelli m In Favor 4 4,L. Peterson Mayor Rosen Against - �\ �'� Mr. President, Dillon . . E 5M 6-56 1 CITY OF SAINT PAUL TERRANCE S. O'TOOLE LEGAL DEPARTMENT LOUIS P. SHEAHAN THOMAS J. RYAN SPECIAL ASSISTANT ROBERT E. O'CONNELL MARSHALL F. HURLEY DONALD L. LAIS JOHN J. McNEIL CORPORATION COUNSEL ASSISTANTS July 8, 1957 1 �� {Jc tie) To the Council : In re: Claim of F. Morettini, Inc. dated September 22, 1956, filed with the Council of the City of Saint Paul September 25, 1957. This letter concerns itself with the above named claim made by the Contractor for asserted costs incurred by it as a result of a so-called "Change Order" during the progress of one of the City' s projects on which said Contractor was low bidder, and was in process of doing the work.. THE FACTS (F. Morettini, Inc. , is hereinafter referred to as the "Contractor" . ) On September 7, 1955, a contract was entered into between the City of Saint Paul and said Contractor under which said Contractor was to furnish all labor and material for the construction of Trout Brook Extension to Rice Street and sewer in Rice Street from Cottage Avenue to Larpenteur Avenue in accordance with plans and specifications issued by the City in connection with said project. This work, of course, had been put out on competitive bidding. Formal Bid was No. 5301. The Contractor was low bidder and was awarded the contract by the City. (See Council Resolution 174462, approved August 30, 1955. ) The City Contract Number is 55-S-465. It bears Comptroller' s Contract No. L-5655. Performance Bond is No. 509181, on file in the office of the Comptroller. Some time after work was initiated by the Contractor, it seemingly became apparent to the parties • I • To the Council 2. July 8, 1957 that extra work would necessarily have to be performed by Contractor in connection with the project , such work being of such type, kind and extent that it could not reasonably have been foreseen and anticipated when the plans and specifications for said project had been issued by the City. (For a detailed and specific account of these difficulties and need for the extra work, see :Ai-. George Shepard' s letter to iarshall F. Hurley, Corporation Counsel , on May 3, 1957 , and June 20, 1957. ) That thereafter a "Contract Change Order" dated February 27, 1956, and executed :arch 2, 1956, was entered into by the parties , signed by the Contractor through its President, the Department of Public Works by Frank D. Marzitelli, Commissioner, and George M. Shepard, Chief Engineer, and countersigned by Joe .-Mitchell, Comptroller of the City of Saint Paul. A copy of this "Change Order" is attached hereto. While a tentative figure following certain itemizations is stated at $38, 932.50, said Order closes with the sen- tence, "The final additional cost will be based on the actual quantities of piling driven and concrete poured. " By letter, dated March 2, 1956, directed to the Commissioner of Public Works , F. Morettini, President of the Contractor, informed the City of his feeling that certain additional costs and items should be made a part of the Change Order. See letter attached. Under date of September 22, 1956, the Contractor addressed a letter to the City Council which was his " bill for extra work performed on the above project. " (See letter attached. ) This letter was intDduced in Council on September 25, 1956, and by that body referred to the atten- tion of the Commissioner of Public Works . The Contractor' s ciaim was in the amount of $158, 692.39 and presented only in category itemization of the type of work completed by it. • To the Council 3. July 8, 1957 The matter of said claim had the attention of the Department of Public Works and Mr. George Shepard following the receipt of said claim. (See Mr. George Shepard' s letter dated December 11, 1956, to F. Morettini, Inc. , copy of which is attached. ) On April 18, 1954, the Commissioner of Public Works , George Shepard and the undersigned met together on the matter of the Contractor' s claim. At this meeting, the undersigned informed the said officials that a "break- down" or detailed inventory of the alleged additional costs should be demanded of the Contractor to support any claim under the aforementioned "Change Order". (See letter of George M. Shepard to F. Morettini, Inc. , dated April 18, 1957, hereto attached. ) Answer to George M. Shepard' s letter of April 18, 1957, was made by Contractor on April 30, 1957. (See letter of F. Morettini, Inc. , signed by C. A. Cheney, dated April 30, 1957, to Mr. George M. Shepard, copy of which is hereto attached. ) At a meeting in the office of the undersigned following receipt of said letter, attended by Mr. Morettini and Mr. Cheney of said Contractor, and Mr. Shepard, Mr. Holmgren, Deputy Commissioner of Public Works, and myself , the said agents of the Contractor were told that supporting data under affidavit by an officer of the corporation would necessarily have to be filed by the Contractor in support of any such claim for extra work and materials assertedly made necessary by reason of the so-called "Change" order. Subsequently, such affidavit and supporting data were furnished by Contractor and are now in the main file relative to said claim. • • To the Council 4. July 8, 1957 At some stage in these proceedings on this claim (the exact date being at this date unknown to the undersigned) and after a detailed check of the records of the Department of Public Works in relation to this project "Change" , the said Department established a reasonable price to be paid for the settlement of this claim made by the Contractor and submitted under the so-called Change Order. The amount determined by the Department as reasonable payment for the extra work involved by reason of the Change Order was in the sum of $75, 374.84. (See correspondence of Mr. George M. Shepard, Street and Highway Engineering Coordinator, to I:r. Marshall F. Hurley, Corporation Counsel , under dates of May 3, 1957, and June 20, 1957. ) CONCLUSIONS We here set out the facts in reference to this matter in chronological fashion so that explanation of such facts may be made more concisely to the Council in this matter. First , we make two points clear as far as this office is concerned. (1) Ours is not the responsibility- to pass on the question of the amount determined to be a reasonable figure for settlement of this claim. The sum of $75, 374.84 as set by the Department seemingly is a reasonable figure. The determination of this figure was founded on bases set out fully in Mr. Shepard's communication to ILr. Hurley of May 3, 1957 , and June 20, 1957. (2) The obligation of this office, as we see it , is to advise the Council as to the legality of the procedure involved in settlement of said claim. eJa advise the Council that it has the power, by resolution, tc approve the additions made in accordance with the specifications and the properly executed "Contract Change Order" in the amount arrived at by the Department of Public Works , and authorize the settlement of the claim made by such Contractor in connection with the said project. • • To the Council 5. July 8 , 1957 The Charter of the City of Saint Paul makes provision for such a "Contract Change Order" as was executed in this matter. (Sec. 95. " * * * No claim or extra labor or material shall be allowed unless the cost thereof has been fully agreed upon by the department for which the labor or material is furnished and the contrac- tor, and a memorandum of said agreement has been filed with the comptroller and countersigned by him prior to the furnish- ing of such extra labor or material. " ) Competitive bidding requirements in a home rule charter do not bar the making of changes or alterations in the plans of a valid written contract for the construction of a public work when • the right to make such changes or alterations is reserved in the contract itself . Carson v. City of Dawson 129 Minn. 453 152 N.W. 842 • Dunnell' s : inn. Digest , 6707 (a ) In the contract between the City and Contractor of -which the project specifications are made a part, we find the following : 1. 31-General Specifications "The Engineer reserves the right to make such reasonable changes , additions or deduc- tions in the plans and specifications as may be necessary to meet exigencies of particular situations when, in the opinion of the Engineer, such changes are necessary or desirable. In which case or cases , if such changes entail an additional expense upon the contractor, an allowance will be made therefor, and if such change or changes reduce the amount of work, labor or material which otherwise would be necessary under the contract , a corresponding To the Council 6. July 8, 1957 deduction will be made from the contract price. The allowance or deduction in either case shall be determined by the Commissioner of Public Works and his determination thereon shall be final. Such determination shall , however, as far as practicable be based upon the unit prices given in the schedule of prices for the same or similar work in these specifications . No allowance will be made for anticipated profits . " We find that the "Contract Change Order" in this particular case answers the requirement of the Charter and the Contract Specifications . One more matter might well receive our comment, and that is the adjustment in this settlement of claim of the prices per cubic yard of Class A and Class C concrete to an agreed price differing from the unit prices in the Schedule of Prices in the Specifications . It appears that the prices for this material as set out in the Specifications for concrete were based on 1948 figures . It is my opinion that any settlement offered by the Department of Public Works in the matter of this claim can properly and legally adjust the figures to the level of unit prices current at the time the Change Order was carried out by the Contractor. Any other basis for the adjustment of this particular item involved in the Change Order would, it appears to me, be wholly inequitable. On the basis of the facts detailed at length hereinabove and on the conclusions which this office has arrived at , we advise you that it is proper for the Council to make settlement of this claim. We furnish you herewith a form of resolution which you may use if , in your discretion, you arrive at the conclusion that the settlement of the disputed claim should be in the amount and for the reasons set out in the said Resolution. Yw 1 trul / if :. arsi�all r. Hurley Corporation Counsel i.'IFH:b 1 Enclosures VA. 5151 • F. MORETTINI C--r cnrtaC onttactot 1416 EAST MARYLAND AVENUE ST. PAUL 6. MINN. March 2, 1956 Commissioner of Public Works CI ty of St . Paul Court House St . Paul , Minnesota Genclemer. : Re : Extra work in connection wit-, tiONTRACT 55-3-46 In your original plans and specifications you specify 330 lineal feet of 810" concrete pipe on piling and saddl . You have now requested an additional 619' supported by piling and saddle. In the City's unit schedule , which we know . s a part o:' the contract , unit prices prepared by your repartment specify a number of extra items including : Class A concrete $ 30 .00 per cubic yard Class C concrete 2 , .00 per cubic yard No items involving steel sheeting , additional dewatering , and additional excavation are listed . If we are to proceed immediately witn this revision in t;;e 619' area , we rightfully should be compensated for the legitimate additional expense not contemplated by either party. As your Engineers know , it is necessary to steel sheet this area in order to dewater to permit pouring the concrete saddle and to maintain the banks in place at this new depth in this unstable ground. We should also be compensated for the dewatering itself in this depth not originally contemplated . We also are now required to excavate an additional 21 feet to provide depth for the saddle , and in addition we are now requested to pour concrete under winter conditions and tai • preheating of the ready-mix and the additional heat and covering required to cure the concrete raises our cost over and above the schedule your office attached to the contract. - p. f;. two - In view of the above , we respectfully request a written approval to a Change Order incorporating tr.ese addition- al costs and itestat :, . Steel Sheetink? I :, 0.0C per '_i^.er - 'oit 2. Addit _oval Dewaterinw $2.0.; per lineal foot, , '. Additional Excavation ner c i;bi c yard �', -37,'--lass A Concrete t ' .0) per ' meal foot of alai I ' In lie .; of per cubi ^ 7 .rd { Class C Concrete V .Ce ,._per : inen fo of Sa,dd Le in lien of 6,2, per cub :-- We are confident our request is just and obvious.y this chane requested by your Department now was not contemplated by si tber party when the Contract was executed. very truly 7 77,41 , F. MOiiE7T1h'I , ent. 1174/s OFFICE OF CITY CLERK � LO&ONtlit BUREAU OF RECORDS US Off .W Court Mow. Paul i�w s.. St. P. 1, .t. , ;; v Sept. 26. Hon. Frank D. Marzitelli Calmar. of Public works Building Dear Sir : The City Council referred to you the attached letter of F. Morettini, Inc . with which he pi esents a bill for extra work on the Trout Brook $ewer 9c- tension, as more fully . ,itlined in the letter &lid statement. The letter was filed in this office by Mr . C. A. Cheney who says that he may be reached at the Athletic Club between 12 and 2. Vr truly y rs , v 'L‘1) Q/41, ye- City Clerk � 2,g 1 910 CITY OF SAINT PAUL - MINNESOTA i ti VA. 5151 F. MORETTANI.I r ;LtD Oencta( eonttacfd€R�• 1416 EAST MARYLAND AVENUE 36 ST. PAUL 6, Mires SEp 25 P'`` Sept*ifillo Ut4. Qls Ismirablo City Courcit ;,t'Y Cl LNn St. Peal. l[iaz. Gott lawn- 1s1- Local Imprevasent Contract for Construction of 'frost crook lztensiea to Rios Street and Sower in Rios street from Cottage Avenue to Larpsntsur Avenue: I. land your herewith our bill for sxtra nark performed on the above project. This antra 'Rork was osussd by a "Change in Plans' made by the amiagssr and vas not included in the original contract. Yours truly, P. Morettinis, Inc. • I -T [1/ 1 --/-‘rileat • • 4 r . • • V r VA:5151 4000 F. MORETTINI gcnetat eonttactot 1416 EAST MARYLAND AVENUE ST. PAUL 6, MINN. April 30, 1957. Ir. Geo. M. Shepard Dept. of Public Works St. Paul, Minn. Dear Sir:- Re:- Contract L-6655 Referring to your letter of Apr.18/57, in which you request information ro,gardinn the cost of the additional work required under this contract, we wish to advise ttbat accurate cost records were not kept on this work. Iowevewer, the writer has c xamiied the available records and the following statement, while apuroxiaate, is probably nearly correct. po-Watering 2 - Pumps , • $5.00 per da. 1 - Pustpman • 20,44 " " 25.44 " " • 47 das. 1,195,68 Ins.& Tail- 9km.Comp. PL.& PD. Soc. Sec. -Camp. $960.68 • 16% 143.71 $ 1,339.39 Concrete • Class • - 547.9 su.yd. • $16.97 9,150.23 " C • 395 " • 12.63 4,988.85 Steel 26132 lb. • .0882 2.304.78 $ 16,443.86 7lacing Concrete Install & Remove Steel Sheet Piling, used for Porno, including timbering- 2 - Draglines • 200.00 per da. 47 des. 9,400.00 Steel Sheet Piling, 4,000.00 Tuber 1,200.00 Labor, $ 36,839.88 Ins. & Tax:- SC. PL &1114 Soc.Sec. Unemp. • 16% 5.894.39 42,734.27 Additional Concrete Cl.A 74 an.yd. • $16.97 1,155.78 C1.0 148 " • 12.63 1.869.68 3.025.46 A 60,359.72 The above are operating costs and do not include the cost of supervision, use of contractors truck,autosobiles, or general overhead expense. ivy /e trust this information will meet your requirements. Tours truly, ' P.YO*Fitl a C. By .. . . . April 1=, '95/ i V. Morsttiai, Las. »noral Contractor 1.4i6 Last M cry land AV". I 3t, raul 6, Minnesota 1 Deer Sir, i Ln oo i sstion mitt: the negotiation for ssttlss►sc i. .,sf extra work performed by you concerning your contract as ted September osr Lt, 1935, for the Trout Hrook earteai ioc t-. :c s 3trset, etc. , Cosaissiaeel` Muraitslli and i had a stseti;s: wilt. Mir. Marshall Hurley, City Attorney, this corning. Mr. ls.. ie;, 4. dseires further lafarmation. ,N'' `: i 1+111 yr ► kladly tbraiat is at your sarliost ooavuoiai. , r'�, a stateasat of seat of detisatmrind tbs 686 feet of edditi: aa: 4... { „ 1 piled sewer. I would also like to here your +osol s is oU l t to! placing of oor creta, both Class "A" and Class "C", i.osiw: nr costs of aaterials, both steel and saberste, for the add'!.tiot;.«i 686 feet of piled ssctiast ordered. This should be brokwa+.bia into labor, materials and equipment, with then p ice per yard paid for Class *A" and Clara "C" oonarete delivered K7i3 tr e price paid for steel. i tv►1rs err;' truly, 1 'rt K. Still F a !•rest and Hi sly way L►ngineering Covrlioator cat C . Naraitelli Arthur W. Two kil t,';c~•.it • . .. y. ► +. • • • Jun r is MM • Mr. Marshall F. Itsrlq Corporation Cvoaael City of St. Paul Rss Ikrettisi Oem rast Treat Ikook Ertassi±oti Contrast 55-5465 5 Dear Mr. Nutley* Ct ptrollsi 's Cattrs*t. I:4655 • On Julie 6, at the meeting in 7 w office gemeeriing the eb e, referenced Morettini claim, Messrs. lforettlmi and Obesity, his rppreeentati'r'e agreed to snteit a detailed statement of the oast of extra work media necessary by the extra work order ' for additional piling and osecrete pipe foundation ordered >4 this departuee t in connection with the oonstroatiee of the foregoing contract. this neeting, on the noraiag of June 12, itr. C. P. Baneon, our Construction lmgiaeer, and I visited the office of F. Morettini, Inc. As I stated to you at the ties of our sorting, there were no records available of breakdown of cost as between excavation, concreting and other pay items. The psall rewords, however, appear to 00' 131 good ..shahs: as is the record of invoice* for materials received. I advised Mr. Mirettini,,. in.oeonea- time with the statement Of cost which he was to prepare, to deficit lyy'tndluide .aaly, items made n oessar7 by the additional west: order and to oiiaiiont as r- cost hick; wield beve boas ioourrsd laird the extra mirk not boos ordered. Ca Awe 1H sr. 7i representing T. Iilaetf iiii Is�a., ps ranted to .t!` departs Rent a statement oil Ostia .laeer, , Mteriel, , et , with,litter, of, �ii�t �pl3i treaaittal dated Jam► 17, �h the-letter and the �t 1t being "eipsd ig Ms. Karettini.. A sely of this statsasut and letter of tratewittal ii ettubsd hereto. - Mr. Cheney stated that Mr. liorettiai wield eign an affidavit mertifyiag ti the aeseracy of the statement and to the fast that the expesditerailmed ba..in rred due • to the extra work order. Zen will mote that certain of the labor and eqpipmemt items begin rrith the week ending February 1, 1936, which is in advisee of the date of tai fork`order. Ia this connection, it lay be stated that as the wish Os the original originel 330 foet of pile sup- ported section pr ooeeded on Nebraska Au.me westerly toward Din , the fesudatice con- dition was unsuitable and additional piling was ordered verbal y:for apporQXinately 130 feet westerly of the vest sad of the 330 foot spatial in 0011.0040 of the-Preparation of the extra verb der. I on attaching hereto a rsour'd : i-fri* e_- di on pile driving. Ion 1111 mote tittle' page 1, erode Operetta' 12, "Matra Pi1i g•; en Jsbraaka Street vest to Bide Street,' pile driving.is *be* on l.>isary 1st to p"a riir; 7th, 1936. This work mod` bsv* bed to be add ley►•the► d Teary avat3on. r:c ak of air comatristi dbolo . isdi+rat is that Ve p we c aririiid ►:d r f eaAdear the attn. vest • - File No. 184001—By Milton 184001 01 ived, That the Council hereb Original to y Clerk es the awa^d •f the Purchas' CITY OF ST. P ''tee the, , ' ''.Fl,.. 'w 4CIL NO. OFFICE OF THE CI i COUNCIL 1 ,..• QN-E -1/4L Fa(NA Atif PRESENTED COMM SSIONE A•011"" r�T`�r r .=-=--a 6 DATF July 31, 1957 RESOLVED, That the Council hereby approves the award of the Purchasing Committee therefor and hereby awards contract for furnishing and delivering to the City of St. Paul Water Department Purification Plant, Soo Line Siding, St. Paul, Minnesota, One Years Supply (to July 15, 1958) - approximately 450 tons - Solvay Liquid Chlorine in carload shipments of 30 tons each, to MATERIAL SUPPLY CORPORATION at a contract price of approximately $38,160.00 f.o.b. point of delivery, in accordance with City specifications and the Formal Bid #6490 of said Material Supply Corporation, said bidder being a reasonable and reliable one and the Corporation Counsel be and hereby is directed to draw up the proper form of contract therefor and the proper City officials hereby are authorized to execute said contract on behalf of the City of St.Paul. Formal Bid #6490. • AUG 21957 COUNCILMEN Adopted by the Council 195_ Yeas Nays DeCourcy Approve t �t�; Holland 195_ Marzitelli /6�snr+incnn In Favor v Mayor Peterson IJ Rosen Against • Mr.�,Pr^e�sident, Dillon 5M 6-56 0 ,.>"', ' °`,, P1JgLIS� l �� Duplicate to Printer 18400/ CITY OF ST. PAUL COUNCIL Na sass OFFICE OF THE CITY CLERK COUNCIL RESOLUTION-GENERAL FORM PRESENTED BY COMMISSIONER DATF July 31, 1957 RESOLVED, That the Council hereby approves the award of the Purchasing Committee therefor and hereby awards contract for furnishing and delivering to the City of St. Paul Water Department Purification Plant, Soo Line Siding, St. Paul, Minnesota, One Years Supply (to July 15, 1958) - approximately 450 tons • Solvay Liquid Chlorine in carload shipments of 30 tons each, to MATERIAL SUPPLY CORPORATION at a contract price of appriximately $38,160.00 f.o.b. point of delivery, in accordance with City specifications and the Formal Bid 706490 of said Material Supply Corporation, said bidder being a reasonable and reliable one and the Corporation Counsel be and hereby is directed to draw up the proper form of contract therefor and the proper City offitials hereby are authorized to execute said contract on behalf of the City of St.Paul. Formal Bid #6490. AUG 21fl67 COUNCILMEN Adopted by the Council 195_ Yeas Nays Ade #11(97 DeCourcy Holland Approved 195_ Marzitelli Mortinson In Favor Peterson Mayor Rosen Against Mr. President, Dillon 5M 6-56 °2