184686Original to City Clerk '
• r .. , CITY OF ST. PAUL
OFFICE OF THE CITY CLERK
PRESENTED BY
COMMISSION
COUNCIL
Adrian P. Winkel
>N- GENERAL FORM
184686
COU
FILENCIL NO.
WHEREAS, in the matter of Comptrollerts Contract L -5863, Phalen Branch
of the Belt Line Sewer Contract ttBt1, Frank Serratore, contractor, the
specified date of completion is August 12, 1957, and
WHEREAS, the contractor has prosecuted the work diligently but
completion of the sewer work was held up pending completion of grading
under a separate contract, it was not possible to complete the contract
until September 16, 1957, therefore be it
RESOLVED, That the proper City officials be and they are hereby
authorized and directed to execute an amendment to said contract
extending the time of completion to September 16, 1957, provided however,
that this resolution,,shall have no force or effect unless the sureties
on the contractor's bond consent thereto and file such consent in
writing with the City Comptroller, and be it
FURTHER RESOLVED, That the City of St. Paul hereby waives all
claims for liquidated damages and that no engineering and inspection
costs on this project will be charged by the City on account of such
extended period
Council File No. 184686 —By Adrian P.
Winkel —
Whereas, In the matter of Comp-
troller's Contract L -5863, Phalen Branch'
of the Belt Line Sewer Contract "B ",
;Frank Serratore, contractor, the speci -'
fled date of completion is August 12, ,
1957, and
Whereas, The' contractor has prose-
cuted the work diligently but com- .
1pletion of the .sewer work was held'
up pending completion of grading'
under a separate contract, it was not
possible to complete the contract until
September 16, 1957, therefore be it
Resolved, That tthe proper City off'-
cials be and they) are hereby author-
ized and directed to execute an amend-
ment to said contract extending the
i time of completion to September 16,
1957, provided however, that this reso-
lution shall have no force or effect
unless the sureties on the contractor's
bond consent thereto and file such
consent in writing with the City Comp-
troller, and be it
Further Resolved, That the City of
St. Paul hereby waives all claims for
liquidated damages and that no engi-
neering and inspection costs on tnis
project will be charged by the City
on account of such extended period.
COUNCILMEN Adopted by the Council October 1,
1957.
Yeas s Approved October 1, 1957.
(October 5, 1957)
TR„r . �_...._
In Favor
Mortinson
Peterson 5,Against
Mr. President, Dillon
5M 6.55 4002 1 \
1.747
Adopted by the Council 195—
OCT
Approved 195_
j,
Mayor
Duplicate to Printer '�_84 6i
CITY OF ST. PAUL COUNCIL NO. JYYff`J 7
OFFICE OF THE CITY CLERK
COUNCIL RESOLUTION — GENERAL FORM
PRESENTED BY ddi� P 6' Winkel DATE 9 '� AJr7
COMMISSIONER ., ombel,
WOW# in the matter Of Cwvtrolleres Contract L.5863,, Phalen Branch
if the Belt Line 561"r'C0Xtract NBO, Frans Se'rra.tore, contractor, the
specified hate Of completion to Autgust 12, 1957s, and
W$EW% the contractor has prosecuted the work diligently but
completion of the sewer work tape held up pending completion of grading
under a separate contract, it was not possible to complete the contract
until September 16, 1957, therefore be it
RMMEB, That the proper City Officials be and they are hereby
authorised and directed to execute an amendment to said contract
extending the time of coMletion to September 16, 195 7s provided however,
that this resolution shell have no force or effect unless the sureties
on the contractor c s bond consent' thereto, and file such douse nt is
writing with the City Comptrener, and be it
FU MO REMLVPU, That the City, of
claims for liquidated damages and—that so
costs on this project will be charged by
extended period.
COUNCILMEN
Yeas aye
Gib
Ifelland— -s-
.m7belk— Tn Favor
Mortinson;r
Peterson Against
Mr. President, Mon
5M 6.55 2
3t. Paul. hereby;saives an
engineering and inspection
the City on account of such
ST ' ,'1zt
Adopted by the Council 195—
06f A 1967
Approved 195—
Mayor