198723r
i
Council File No .... ...............................
0
198723
CITY OF ST. PAUL
Resolution Ratifying Assessment
In the matter of the assessment of benefits, cost and expenses
for
constructing a sewer in Danforth Street from Nebraska, Avenue to a.point 455 feet south
of the south line of Nebraska. Avenue
under Preliminary Order .... 179895. ......... , Intermediary Order
approved......... S. �PUMbeZ..1.7..........19 -57..
A public hearing having been had upon the assessment for the above
having been further considered by the Council, and having been considered
Council File No. 198723—
In the matter of the assessment of
benefits, cost and expenses for con-
structing a sewer in Danforth Street
from Nebraska Avenue to a point 455
feet s o u t h of the south line of
Nebraska Avenue, under Preliminary
Order 179895, Intermediary Order
184233, Final Order 184561, approved
September 17, 1957.
A public hearing having been had
upon the assessment for the above
improvement, and said assessment
having been further considered by the
Council, and having been considered
finally satisfactory, be it therefore
Resolved, That the said assessment '
be and the same is hereby in all re-
spects ratified, and the same is hereby
ordered to be submitted to -the District
Court of the County of Ramsey for
confirmation.
Be It Further Resolved, That 'the
said assessment be and it is hereby
determined to be payable in 5 equal t
installments.
Adopted by the Council August 31, 1e
1960.
Approved August 31, 1960.
File 13847
(September 3, 1960)
RESOLVED, That the said assessment be and the same is hereby in all respects ra 1 e — ana - ,une -sauce
is hereby ordered to be submitted to the District Court of the County of Ramsey for confirmation.
BE IT FURTHER RESOLVED, That the said assessment be and it is hereby determined to be payable
in ...............
......................... equal installments.
AUG 311%0
Adopted by the , CounciL.................... ............................ ....................19.........
AUG 311960
Approved................ _...._.: ---------------------------- 19--------
Form B. B. 18
File 13847
r
114 7 -(... ..... v_�City Clerk.
- - ----------- - - - - -• :..........__.._... ,Mayor.
CITY OF ST. PAUL
i OFFICE OF THE COMMISSIONER OF FINANCE
Report of Completion of Assessment 1982 6
4
In the matter of the assessment of
AUgalst P, 1q(-'0
benefits, cost and expenses
for
constructing a sewer in Danforth Street from Nebraska Avenue to a point 455 feet south
of the south line of Nebraska Avenue
under Preliminary Order 179895 approved October 3, 1956
Intermediary Order i8�+2B , approved August 20, 1957
Final Order 184561 , approved September 17, 1957
To the Council of the City of St. Paul:
The Commissioner of Finance hereby reports to the Council the following as a statement of the ex-
penditures necessarily incurred for and in connection with the making of the above improvement, viz:
Cost of construction . ............................... $ 3x596.00
' Engineering ............ ..........................$ 260•58--
Inspection fees ...... ..............................$ 71.92
Postal cards ......... ..............................$ 3.30 _
Publications ........ ..............................$ 33.00
Court costs for confirmation ........................ $ 3.30
Total expenditures ....... ......................$ 3.968.10
Said Commissioner further reports that he has assessed and levied the total amount as above ascer-
tained, to -wit: the sum of $ 3,968.10 upon each and every lot, part or parcel of land deemed
benefited by the said improvement, and in the case of each lot, part or parcel of land in accordance with
the benefits conferred thereon; that the said assessment has been completed, and that hereto attached,
identified by the signature of the said Commissioner, and made a part hereof, is the said assessment as
completed by him, and which is herewith submitted to the Council for such action thereon as may be
considered proper.
2M 12 -62 g Commissioner of Finance.