WHEREAS, in the matter of the construction of the STORM AND CLEAR
WATER SEWER in Sixth Street from St. Peter Street, thence east
222 feet, Comptroller's Contract L -6650, Axel Newman Heating and
Plumbing Company, contractor, designed to serve the new Wabasha
Court Building.,-located on the northwest corner of Sixth and
Wabasha Streets, the specified date of completion is July 1, 1964,
and
WHEIEAS, the previsioned completion date made a part of the Special
Provisions of said project on the basis of information sufficient
to form a belief by the design engineer that the new Wabasha Court
Structure would be in need of such sewer service at that time, and
WHEEE AS, it became apparent later that the necessity of completing
the work by said expiration date was not urgent and that an exten-
sion of time to:a later date would result in no hardship-to the
parties in interest, now therefore, be it
RESOLVED, That the proper City Officers be and they are hereby
authorized and directed to execute an amendment to said-contract
extending the time for completion to SEPTEMBER 4. 1964, provided
however, that this resolution shall have no force or effect unless
the sureties on the contractor's bond consent thereto in writing
and file such consent with the City Comptroller, and be it -
FURTHER RESOLVED, That the City of St. Paul hereby waives all claim
for liquidated damages and that no engineering and inspe ct#n costs
on this project will be charged to the contractor on account of
such extended period. ri
COUNCILMEN
Yeas Nays
- Dalglish
Holland
Loss
*Aered th
Peterson
Rosen
Mr. President, Vavoulis
font 6-62
SAP 1�
Adopted by the Council 19—
SEP 18 04
Approved 19—
To Favor
� Mayor
Against
DUPL&AT[ TO PRINTER
CITY OF ST. PAUL COUNCIL NO 'U!
OFFICE OF THE CITY CLERK FILE
COUNCIL RESOLUTION — GENERAL FORM
PRESENTED BY
COMMISSIONER DATE
WHEREAS, in the matter of the construction of the STORM AND CLEAR
WATER SEWER in Sixth. Street from St. Peter Street, thence east
222 feet., Comptroller +s Contract L -6650, Axel Newman Reating and
Plumbing Compa.nyk contractor# designed to serve the new Wabasha
Court Building; located on the northwest corner of Sixth and
Wabash.& Streets, the specified date of completion is July 1, 19641
and
MJEHEAS, the previsioned completion date made a part of the Special
Provimione of said project on the basis of information sufficient
to form a belief by tb3 design engineer that the new Wabash& Court
Structure would be in need of such sewer service at that time, and
WHEff AS, it became apparent later that the necessity of completing
the work by said expiration date was not urgent and that an exten-
sion of time toLa later date would result in no hardship to the
parties in interest, now therefore, be it
RESOLVED, That the proper City Officers be and they are hereby
authorised and directed to execute an amendment to said contract
extending the time for completion to SEPTEMBER 4, 1964, provided
however, that this resolution shall have no force or effect unless
the sureties on the contractorfs bond consent thereto in writing
and file such consent with the City Comptroller, and be it
FURTHER RESOLVED, That the City o
for liquidated damages and that
on this project will be charged
such extended period.
COUNCILMEN
Yeas Nays
Dalglish
Holland
Loss
Meredith__.
Peterson
Rosen
Mr. President, Vavoulis
10M a-as
f St. Paul hereby waives all claim
no engineering and inspo eti5n coats
to the contractor on account of
6