226126ORIGINAL TO CITY CLERK
PRESENTED BY
COMMISSION
CITY OF ST. PAUL
OFFICE OF THE CITY CLERK
UNCIL RESOLUTION - GENERAL FORM
COUNCIL NO. 226126
FILE
WHEREAS, The Saint Paul City Council, pursuant to Resolu-
tion C.F. No. 221353, approved January 6, 1965, awarded the con-
tract for construction of the Trout Brook Sewer Extension Repair
No. 2 Interstate Highway 35E and Vicinity of Maryland Avenue to
Hurley Construction Company for the contract price of $67,992.00,
said contract price among other things being based on Hurley Con-
struction Company furnishing and driving 34 steel "H" piles -
10 BP 42 #,
WHEREAS, After completion of said construction the records
of the Department'of Public Works show that Hurley Construction
Company drove 2,8+8.6 lineal feet of the 4,080 lineal feet of
steel piling orde'red pursuant to said contract and said company
-does now request an adjustment in the Unit Price for increases
or decreases for piling driven. now therefore be it
RESOLVED, That Contract No. L -6722, Project No. 64 -5 -969,
dated January ll „ 1965, by and between the City of Saint Paul
and Hurley Construction Company be and the same is hereby adjusted,
due to the decrease in footage of steel piling driven, so as to
reduce said contract price by the sum of $3,18+.75, according to
the formula contained-in the attached letter, dated November 1,
1965, signed by C. P. Hanson, Construction Engineer, Department
of Public Works, ,subject to Hurley Construction Company filing
with the Comptroller its acceptance of the terms hereof in writing
and in form approved by the Corporation Counsel.
1
COUNCILMEN
Yeas
Dalglish
Holland
Loss
Meredith
Peterson
- toseff--
Nays
ee14�
Mr. Vice President (Rosen)
font "2
DEC 210
Adopted by the Council 19-
®�D �g65
roved 4 19—
Tn Favor l
L9 ` '/ Mayor
Against
mumm DEC 41965
DUPLICATE TO PRINTER
• CITY OF ST. PAUL • I COUNCIL NO.
OFFICE OF THE CITY CLERK FILE
COUNCIL RESOLUTION — GENERAL FORM
PRESENTED BY
COMMISSIONER DATE
Yeas
WHEREAS, The Saint Paul City Council, pursuant to Resolu-
tion C.F. No. 221353, approved January 6, 1965, awarded the con-
tract for construction of the Trout Brook Sewer Extension Repair
No. 2 Interstate Highway 35E and Vicinity of Maryland Avenue to
Hurley Construction Company for the contract price of $67,992.00,
said contract price among other things being based on Hurley Con-
struction Company furnishing and driving 34 steel "H" piles -
10 BP 42#0
WHEREAS, After completion of said construction the records
of the Department of Public Works show that Hurley Construction
Company drove 2,848.6 lineal feet of the 41 080 lineal feet of
steel piling ordered pursuant to said contract and said company
does now request an adjustment in the Unit Price for increases
or decreases for piling driven, now therefore be it
RESOLVED, That Contract No, L -6722, Project No. 64 -5 -969,
dated January 11, 1965, by and between the City of Saint Paul
and Hurley Construction Company be and the same is hereby adjusted,
due to the decrease in footage of steel piling driven, so as to
reduce said contract price by the sum of $3,184-75, according to
the formula contained in the attached letter, dated November 1,
1965, signed by C. P. Hanson, Construction Engineer, Department
of Public Works, subject to Hurley Construction Company filing
with the Comptroller its acceptance of the terms hereof in writing
and in form approved by the Corporation Counsel.
COUNCILMEN
Dalglish
Holland
Loss
Meredith
Peterson
„it°s -L
Nays
..Mr...Pre s ident,.- Yavoulis'I
....... .. ....
... .......�.._......... :..._:::...
4`'011 VFW Prce.dent (Rosen;
Tn Favor
O
Against
DE-c 2 A0
Adopted by the Council 19—
DEC 9, 10
Approval 19—
Mayor
-
`-~• t1 Ift
mot" 4 r 1.. I
;GEORGE M. SHEPARD 1 3 -
STREET AND HIGHWAY C I • l Of S A I N T: SPA �U �:L. y R ;; M w EUGENE; I AVERY
_ _ V M M CHIEF ENGINEER'�r`�"••4`
.�... -� ENGINEERING COORDINATOR � �, .• � _ - ^ Y 1;,� E * G - " � 1� 1 �
I ., Capital of Minnesota - i ." ='c vOK _-
_ _ _ — OUN; JR.
-PUBLIC�WORKS.- " r = - ' SUPERINTENDEN
DEPARTMENT -OF T�OF SANITATION
,•
234 QtyHd11'. , Court Hcuse 55102-
M TON RO -SE1V iii 1i►► :' i itj� im �.. rl •� _`_.
�11� . `,.r _ r.., •, Commissioners_ 1'�1 nu ,.y, t� �I L _�
x.•- T` j,.q.'L�;`iiL`",.w*���!LII�GIAM P: BEHRENS
s r -r Deputy Commissioner.' --
November 1, 1965
Corporation Counsel,
316 City Hall
1
Attention: Mr. Jerome Segal
Re: Trout Brook Sewer Repair #2
Project No. 64 -S -969
t
Dear Mr. Segal: ;
I
The enclosed copy of our pile driving report for this project shows that
2848.6 lin. ft. of steel piling were driven, leaving 1231.4 lin. ft. not driven
out of a total of 4080 feet ordered.
20% of the total number is 816 lin. ft. which will be subject to the
contract price of $5.00 per lin. ft. for deduction and the remainder of 415.4
lin. ft. would be deducted at the rate of $1.42 per ft. in accordance with the
terms of the proposed agreement.
Due to the fact that the Contractor had to order the total amount of
steel piling immediately, leaving him with 1231.4 lin. ft. of steel piling not
driven, the agreement proposes to allow the Contractor the net cost to him of
the 816 lin. ft. for which the full deduction is taken. This would be at the
rate of $1.82 per ft. based on the actual cost of $0.0733 per lb. less salvage
value of $0.03 per lb. or a net of $0.0433 per lb. for 42 lbs.per ft. which is
$1.82 per ft.
In summary, the proposed settlement is as follows:
20% of 4080 lin. ft. = 816 x 5.00 = $4080.00
415.4 x 1.42 = 589.87
Gross Deduction $4669.87
Allowance to Contractor:
For piling not driven 816 x 1.82 = $1485.12
Net Deduction $3184.75
This should cover the deduction due to the pile driving operation.
'965 't�0
P �
C� C
� GO
CPH /gs
Enc.
Yours very truly,
DEPARTME 0 PUBLIC WORKS
C. P. Hanson
Construction Engineer
Csi`ORGE M. SHEPARD 1 CITY O F SAINT. PA U L { EUGENE V. AVERY
STREET AND HIGHWAY CHIEF ENGINEER
ENGINEERING COORDINATOR
Capital of Minnesota
{ , C. J. VOKOUN, JR.
DEPARTMENT OF PUBLIC WORKS . - fUrERINTEHDENT of SANITATION
234 City Hall & Court House 55102:.
MILTON ROSEN
Commissioner
WILLIAM P. BEHREN3
�...» ^., Deputy Commissioner
November 1, 1965
Corporation Counsel
316 City Hall
Attention: Mr. Jerome Segal
Re: Trout Brook Selver Repair #2
Project No. 64r.S -969
Dear Mr. Segal:
The enclosed copy of our pile driving report for this project shows that
2848.6 lin. ft. of steel piling were driven, leaving 1231.4 lin. ft. not driven
out of a total of 4080 feet ordered.
20% of the total number is 'r lin. ft. which will be subject to the -
contract price of $5.00 per lin. ft. for deduction and the remainder of 415.4
lin. ft. would be deducted at the rate of $1.42 per ft. in accordance with the
terms of the proposed agreement.
Due to the fact that the Contractor had to order the total amount of-
steel piling immediately, leaving him with 1231.4 lin. ft. of steel piling not
driven, the agreement proposes to allow the Contractor the net cost to him of
the 816 lin. ft. for which the full deduction is taken. This would be at the
rate of $1.82 per ft. based on the actual cost of $0.0733 per lb. less salvage
value of $0.03 per lb. or a net of $0.0433 per lb. for 42 lbs.per ft. which is
$1.82 per ft.
In summary, the proposed settlement is as follows:
20% of 4080 lin. ft. 816 x 5.00 $4080.00
415.4 x 1.42 589.87
Gross Deduction $4669.87
Allowance to Contractor:
For piling not driven 816 x 1.82 = $1485.12
Net Deduction $3184.75.
This should cover the deduction due to the pile driving operation.
Yours very truly,
r 'v �� 65' DEPARTME 0 PUBLIC WORKS
0,10 19
CD C.T. Hanson
g Construction Engineer
CPH /gs
Enc.
QEOR•GE M. SHEPARD EUGENE V. AVERY
STREET AND HIGHWAY CITY O F SAINT PA U L «; ' CHIEF ENGINEER
ENGINEERING COORDINATOR T }� a ,.
Capital Hof Minnesota Z", C. J. VOKOUN, JR.
U DEPARTMENT OF PUBLIC WORKS : " - _ SUPERINTENDENT OF SANITATION
234 City Hall & Court House 55102 . _ .1
MILTON ROSEN
Commissioner
;,.r. WILLIAM P. BEHREN3
Deputy Ccmm4sfoner. r y
f November 1, 1965
Corporation Counsel _
316 City Hall '
Attention: Mr. Jerome Segal
Re:- Trout Brook Sewer Repair #2
Project No. 64 -5 -969
Dear Mr. Segal:
The enclosed copy of our pile driving report for this project shows that
2848.6 lin. ft. of steel piling were driven, leaving 1231.4 lin. ft. not driven
out of a total of,4080 feet ordered.
20% of the total number isf 816 lin. ft. which will be subject to the -
contract price of $5.00 per lin. ft. for deduction and the remainder of 415.4
lin. ft. would be deducted at the rate of $1.42 per ft. in accordance with the
terms of the proposed agreement. ,
Due to the fact that the Contractor had to order the total amount of"
steel piling immediately, leaving him with 1231.4 lin. ft. of steel piling not
driven, the agreement proposes to allow the Contractor the net cost to him of
the 816 lin. ft. for which the full deduction is taken. ° This would be at-the
rate of $1.82 per ft. based on the actual cost of $0.0733 per lb. less salvage
value of $0.03 per lb. or a net of $0.0433 per lb. for 42 lbs. per ft. which is
$1.82 per ft.
" In summary, the proposed settlement is as follows:
20% of 4080 lin. ft. 816 x 5.00 $4080.00
415.4 x 1.42 = 589.87
Gross Deduction $4669.87
Allowance to Contractor:
For piling not'driven -•816 x 1.82 = $1485.12
r- Net Deduction $3184.75
This should cover the deduction'due'to the pile driving operation.
Yours very truly, -
i
� C
CPH /gs
Enc.
DEPARTME 0 PUBLIC WORKS
C. P. Hanson
Construction Engineer
t