WHEREAS, in the matt9r of Comptroller's Contract L- 6801 -1 for
the construction /a WATER N,AIN on the NAVY ISLAND BRIDGE,
Healy Plumbing and Heating Company, contractor, the specified,
completion date is December 10, 1965, and
WHEREAS, the work was prosecuted assiduously by said contractor,
but due to a delay in securing delivery of a patented pipe joint
device coupled with a slower installation of pipe protectives
on account of unfavorable weather conditions, it was not possible
to complete the contract by said date of completion; therefore,
be it
RESOLVED, That the proper City Officers be end they are hereby
authorized and directed to execute an amendment to said contract
extending the completion date to JANUARY 7, 1966, providedlhowever,
that this resolution shall have no force or effect unless the
sureties on the contractor's bond consent thereto in writing and
file such consent with the City Comptroller, and be it
FURTHER RESOLVED, that the City of Saint
claim for liquidated damages and that
costs on this project will be charged
of, such extended period.
COUNCILMEN
Yeas Nays
Dalglish
Holland
Loss
Meredith
Mr. Pres>3l+iz. tTe—It,
n
ions 6-62
Paul hereby waives all
no engineering and inspection
to the contractor on account
.1
FEB _41966
Adopted by the Council 19-
EEB 41966
1 A oved 19-
Tn Favor
U Mayor
Against
PUBLISHED FEB 111966
DUPLICATE TO rRINT[R
227142
CITY OF ST. PAUL FILE NO NO
OFFICE OF THE CITY CLERK
COUNCIL RESOLUTION — GENERAL FORM
►RESENTED BY Feb 66
COMMISSIONED DATE February 1 9
WHEREAS, in the mat &lor of Comptrollert s Contract L- 6801 +1 for
the construetiony/a WATER MAIN on the NAVY ISLAND BRIDGE,
Healy Plumbing and Heating Company,. contractor, the specified
completion date is December 10, 19651 and
WHEREAS, the work was prosecuted assiduously by said contractor#
but due to a delay in securing delivery of a patented pipe joint
device coupled with a slower installation of pipe protectives
on account of unfavorable weather conditions, it was not possible
to complete the contract by said date of completion, therefore,
be it
RESOLVED# That the proper City Officers be and they are hereby
authorized and directed to execute an amendment to said contract
extending the completion date to JANUARY 7# 1966s provided however
that this resolution shall bave no force or effect unless the
sureties on the contractor's bond consent thereto in writing and
file such consent with the City Comptroller, and be it
FURTHER RESOLVED, that the City of Saint Paul hereby waives all
claim for liquidated damages and that no engineering and inspection
costs on this project will be charged to the contractor on account
of such extended period.
FEB 4 IBM
COUNCILMEN Adopted by the Council 19—
Yeas Nays
Dalglish FEB 41966
Holland Approved 19—
Loss fn Favor
Meredith
Mayor
Peterson
Against
- -Roses
M+ President; V"6U1i
font 4-62