Whereas, In the matter of Comptroller's Contract L -6854 for the
Grading and Surfacing of 'WINONA STREET from Brown Avenue to Andrew Street;
Also a Sewer in WINONA STREET from Brown Avenue to Andrew Street, Armor -
-Coat Company, Inc., contractor, the specified date of completion is
September 1, 1966, and
Whereas, The contractor has prosecuted the work diligently but due
to extra work involved in revising the grade line it was not possible
to complete the contract by said date of completion, therefore be it,
Resolved, That the proper City Officials be and they are hereby
authorized and directed to execute an amendment to said contract extending
-the time of completion to October 15, 1966 provided however, that this
•resolution shall have no force or effect unless the sureties on the Con-
'tractor's bond consent thereto and file such consent in writing with the
City Comptroller, and be it,
• Further Resolved, That the City of Saint Paul hereby waives all
claim for liquidated damages and that no engineering and inspection costs
on this project will be charged to the Contractor for such extended period.
COUNCILMEN CCT 111966
Yeas Nays Adopted by the Council 19—
Carlson OCT 111966
Dalglish
/ Approved 19—
Holland
Meredith In Favor
Peterson I Mayor
- Tedescu A gainst
Mr. President, Byrne PUBLISHED OCT 16 1866
22
DUPLICATUTO PRINTER 23047
CITY OF ST. PAUL COUNCIL NO. _
r OFFICE OF THE CITY CLERK
COUNCIL RESOLUTION — GENERAL FORM
PRESENTED BY
COMMISSIONER Robert F. Peterson DATE
'Whereas, In the matter of Comptroller's Conttact.L -6854 for the
Grading and Surfacing of WIN INA STRENT from Brown Avenue to Andrew Street;
Also a Sewer in WMNA STRFlST from Brown Avenue to Andrew Street, Armor -
Coat Company, Inc., contractor, the specified date of completion is
September 1, 19660 and
Whereas$ The contractor has prosecuted the work diligently but due
to extra work involved in revising the grade line it was not possible
to complete the contract by said date of completion, therefore be it,
Resolved, That the proper City Officials be and they, are hereby
authorised and directed to execute an amendment to said contract extending
the time of completion to October 15, 1966 provided however, that this
resolution.shall have no force or effect unless the sureties on the Con -
tractor's bond'consent thereto and file such consent in writing with the
City Comptroller, and be it,
Further Resolved, That'the City of Saint Paul hereby waives all
clate,for liquidated damages and that no engineering and inspection costs
on this project will be charged-to the Contractor for such extended period.
OCT 1119%
COUNCILMEN
Adopted by the Council 19—
Yeas Nays
Carlson OCT 111966
Dalglish Approved 19—
Holland
Meredith In Favor
Peterson D Mayor
I—Pe escTo— Against
Mr. President, Byrne
a2