D00737• • PROJECT: Saint Paul Civic Center Expansion Project Saint Paul, Minnesota CONTRACTOR Edward Kraemer 8� Sons 1020 West Cliff Road Burnsviile, MN 55337 Original Contract Amount $5,317,785.70 CO No. Deduct Add C1.1 14,844.30 C 1.2 7,104.85 C1.3 28,810.80 C1.4 9,928.70 C 1.5 24241.68 Subtota� .00 �84.930.33 DATE ISSUED: 15 August 1995 CONTRACT NO.: CP-1 CONTRACT TITLE: Demolition, Excavation 8� Bridge Construction CONTRACT DATE: 29 March 1995 Net Amount of Contract including this Change Order: $5,402,716.03 • r� S • June 30, 1995 Susan Jones CPMI f.A. O'Shaughnessy P{aza 143 W. Fourth Street St. Paul, MN 55102-1299 ���� 32 s-5�oi.3 K � EBWARD KRAEMER & SONS, INC. Re: C.P. 1, St. Pauf Civic Center Demolition, Excavation and Bridge Gonstruction Concrete Removal in West Bound Kellogg Boulevard DearSusan: As a foilow up to our fetter of June 28th, 1995, regarding the reinforced concrete • pavement encountered on west bound Kellogg Blvd. during Siage 11 removais, we are submitting our cost for the extra work. Please review and issue a contract change order for this work. As of this date we stiA have not received a contraot change order for the concrete pavement removal on Stage 1 that was submitted on 5119195. / If you should have any questions, pfease contact me at (612) 890-2820. Sincerely, ��� Jerry A. Voiz Regional Operations Manager enc. cc: Mike Moe11er1Ames CONSTRUCTION D/VISION � 1020WEST CIIfF ROAD BURNSVILLE, MWNESOTA 33337 612-84Q-2820 FAX- 612-8942996 � AnE9wlpppom�myEmPbY�� �....� � JUC'.29'95 16:23 FR AMES HURNSVILLE CJ _ � 7une 29,1995 612 435 7142 TO KRREMER HVILLE P.01i01 C�-�ae) AMES CONSTRUCTION, INC. �� l 14420 COUNTY ROAD 5 BI3RNSVII.LE, MLNNFSOTA 55306 (612) 435-'7106 • FAX 435-7742 Eciward Kraemcr & Sons, Inc. 1Q2Q WestCliffRoad Burnsville, Minnesota 55337 Atteation: Jexry Volz, Regional Mana$et Subject Concrete Removat in West Bound Kellogg Bouievsrd Saint Yaul Givic Center �xpansion Cp-1 Demo, F.xca�ation & Bridge Construction Dear Jerry: As per our previaus letters conceming the reinForced concrete in east bound Keilogg Boulevard, � we azs scefdng additiona! compensation for the concrete paving encouutered during demoliGon ofthe west bound Kefiogg Baulevard in Phasc II af the referenced project. As outtined ia previous correspandeace, onr additionai cost for removal of this material is $9.72 P� $9� Y� The total exGa cost is thereforc 2,494 �qaare yards at $9.72 or $24,241.68. T6is conczete paving was verified in the field by Eriks L.udins. It is our request that a change order be issued for this amamt If you have any questians, pleasc give me a ca1L Sinccrely, � I�-^� � M'ichael Moeller Project Manager. / M��n� OPPiCES 7N: DfiNVp3, CO[ARAT�O • PA08NDC. AWZONiA � 5AL? L�iK6 CS1Y. Vl'AH ** TOTRL PAGE.H01 �* • lJ t R'S PROPO-S-AL __ __ Contractor Proposaf No.: / ✓ Date: Project:�ain[ Paui Civic Center Contract No.:. A change in the scope of the work is requested as indicated befow: It +s requested the completion date be ( extended, () decreased, !) unchanged by _ calendar days_ The adjusted compietion date wi(i be cu,n..�.� b� � o�... 2. Description of the change: (Refer to drawings, specifications, addenda, if applicable}. {Reference RFP No.: • CCD No.: • FO No.: 1 Basis ot payment: ICheck one) S� ( y Firm price for performing tfiis change is ....:...............................$ Z55toS Adequate supporting detaiis and information (Increased educt) must 6e attached to atlow Owner to evaluate_ () Time and material per contract, but not to exceed $ ( 1 Acival cost at compietion of work S Submitted 6y: �cii.,�a¢,� K-¢'�+aw..�- � S�.- � Date: � � s Contractor � A�1�� Corttractor Sig ature FOR CPMI USE Action Recommended: lCheck one) () Change witl not be made. Explain: 2. CPMt Job No.: 3225 ( l Proceed on the following basis: () As indicated above, change and basis of payment is acceptable. () Change is acceptabte, basis of payment is not acceptable. {) Basis of payment shafi be $ (� The follawing modification is recommended: (� Change in completion date is accepted. ( y Change is acceptable with no. change in price. () Change is acceptabie with no change in completion date. Reasonfor Change: ( � Design Change i! Client Request i) F�eld Condition () Suggested by Contractor () Design Omission or Other (expiain) 3. Is this a part of the originaal contract scope? () YES ( 1 NO 4. Is Contractor's Estimate attached? () YES 1) NO 5. AIE consulted. () YES () fV0 Prepared by: CPMq Approved by (HGA) Approved by (Owner! cc: Eriks Ludins 3225- Date: Date: 3225- Bl SAINT PAUL CIVIC CENTER EXPANSION � • . BREAKDOWN SHEET CONTRACTOR'S PROPOSAL SAINT PAUL CIVIC CENTER EXPANStON LABOR, MATERIAL & EQUIPMENT DIRECT EMPLOYEE LABOR MATERIALS & EQUIPMENT INCORPORATED TOTAL LAB & MATERIAL & EQUIPMENT 15% FEE TOTAL LABOR, MATERIAL, EQUIP., & FEE � S S SUBCONTRACTORS $ 5%FEE Z4 Sy �. � � S \ SOTALSUBCONTRACTORS & FEE OTHER COSTS TRAVEL & SUSSISTENCE MATERIALS & EQUIPMENT NOT INCORPORATED RENTALS TAXES PERMITS & LICENSE FEES UTILITIES, FUEL, FAC{LITIES AT SITE INCIDENTALEXPENSES BOfVD & INSURANCE PROVISfONS TOTAL OTHER COSTS TOTAL OF CHANGE PROPOSAL S S 5 S S S S ��3�1 $ S ° s 'zS S b3 $ ZS sb3� SAINT PAUL CIVIC CENTER EXPANSION